Identity Lifecycle & Provisioning — Project Plan

1. Overview

This plan describes how the Identity Lifecycle & Provisioning project will move from manual or semi-automated identity changes to a governed path in which every joiner, mover, leaver, and non-human identity event originates from an authoritative source, carries an authorization, executes under least privilege, closes with provenance, and emits evidence.

It follows the approach in the project charter: Designate origins → Normalize attributes → Pilot joiner/mover/leaver → Extend to privileged access → Institutionalize review.

2. Guiding Constraints

  • The HR system (or designated equivalent) is the authoritative origin for human organizational placement.
  • The directory is the system of record for identity, not for organizational truth.
  • Access is driven by attributes; manual group membership is an exception.
  • Elevated privilege is time-bounded and scoped.
  • Every change closes with provenance; evidence is a byproduct of the change path.

3. Phases

Phase 0 — Charter and Alignment

Objective: Confirm scope, stakeholders, and the authoritative origin.

Key activities - Review and accept the project charter. - Confirm the HR system (or equivalent) as the authoritative origin for human lifecycle events. - Identify owners for non-human identity classes in scope. - Agree on evidence and provenance expectations.

Deliverables - Accepted charter. - Stakeholder and role list. - Named authoritative origins per identity class.

Exit criteria - Leadership can state which system is authoritative for human lifecycle events and who owns each non-human class.

Phase 1 — Attribute Normalization

Objective: Ensure the attributes that drive access are populated and consistent.

Key activities - Inventory the organizational attributes required for dynamic membership and administrative-unit scoping. - Compare HR source values to directory values; classify discrepancies as drift. - Populate missing attributes for the pilot population. - Document the match key between the HR person identifier and the directory employee identifier.

Deliverables - Attribute inventory. - Drift findings for the pilot population. - Match-key confirmation.

Exit criteria - Pilot population attributes are populated and reconcilable to the authoritative source.

Phase 2 — Pilot Joiner / Mover / Leaver

Objective: Execute the five-clause path for a limited population and validate evidence.

Key activities - Select a pilot population (recommended: one business unit or a controlled set of roles). - Implement joiner, mover, and leaver flows that originate from the HR source. - Require authorization, least-privilege execution, and provenance closure. - Emit evidence for each change. - Detect and classify any drift that appears.

Deliverables - Operational joiner/mover/leaver flows for the pilot. - Provenance records and evidence package. - Lessons-learned summary.

Exit criteria - At least one full joiner, one mover, and one leaver have been executed with provenance and evidence.

Phase 3 — Privileged Access and Just-in-Time Elevation

Objective: Reduce standing privilege for at least one administrative role class.

Key activities - Inventory standing administrative privilege in the pilot scope. - Introduce just-in-time elevation for one privileged role class. - Document break-glass procedures and exclude break-glass accounts from standard policy. - Begin reducing standing privilege for the targeted class.

Deliverables - Just-in-time elevation procedure. - Break-glass account inventory and governance notes. - Standing-privilege reduction report.

Exit criteria - Just-in-time elevation is available and has been used for the targeted role class; standing privilege for that class is measurably reduced.

Phase 4 — Access Certification and Steady-State Drift Detection

Objective: Institutionalize review and continuous detection of identity drift.

Key activities - Define the access certification cadence and scope (privileged and high-blast-radius entitlements first). - Execute the first certification cycle. - Stand up or refine continuous drift detection between the authoritative source and the directory. - Transition ownership to steady-state operations.

Deliverables - Access certification procedure and first-cycle results. - Operational drift detection for identity attributes. - Residual-risk and ownership transfer notes.

Exit criteria - First certification cycle is complete; drift detection is operational; ownership has transferred.

4. Domain Workstreams (Summary)

Domain Primary Focus Suggested Position
Human lifecycle Joiner, mover, leaver from HR source Phase 2
Attribute model Dynamic membership and administrative-unit scoping Phase 1
Privileged access Just-in-time elevation and standing-privilege reduction Phase 3
Non-human identity Service accounts, application registrations, device owners Parallel with Phase 2–3
Access certification Review cadence for high-risk entitlements Phase 4

5. Governance and Decision Rights

  • Sponsor approves source-of-truth designation, major scope changes, and residual risk acceptance.
  • Project lead owns sequencing and cross-domain dependencies.
  • Domain leads own flow design, evidence readiness, and domain-specific residual risks.

6. Risks and Mitigations (Selected)

Risk Mitigation
Incomplete HR data Attribute normalization phase before any access changes; pilot limited to well-populated populations
Legacy service accounts cannot move to managed identity Inventory and owner assignment first; managed identity as a later wave
Resistance to just-in-time elevation Pilot one role class; document break-glass; measure reduction rather than mandate elimination
Non-human identities lack owners Require owner assignment as an entry criterion for lifecycle controls

7. Success Measures (Project Level)

  • Authoritative origins designated and documented.
  • Pilot joiner/mover/leaver flows executed with provenance and evidence.
  • Attribute-driven access operational for the pilot; residual manual membership inventoried.
  • Just-in-time elevation available and standing privilege reduced for at least one role class.
  • First access certification cycle complete.
  • Drift detection operational between the authoritative source and the directory.

8. Immediate Next Actions

  1. Review and accept this plan against the project charter.
  2. Confirm the authoritative origin for human identity lifecycle events.
  3. Inventory non-human identity classes and name owners.
  4. Define the pilot population.
  5. Document the attributes that will drive dynamic membership.

This plan is a project artifact. It incorporates the modernization concepts of authoritative origin, attribute-driven structure, explicit drift, and controlled evidence-producing change. It contains no internal architectural decision record identifiers.