Modernization Project Plan

1. Overview

This plan describes how the modernization project will move from the current state (implicit governance encoded in legacy directories and fragmented stores) to a target state defined by a single authoritative origin for structure and claims, attribute-driven constructs, explicit drift detection, and controlled, evidence-producing change.

It follows the approach in the Project Charter: Assess → Define target → Plan waves → Execute under control → Validate and sustain.

The plan is organized by phases. Each phase has objectives, key activities, deliverables, entry/exit criteria, and notes on risks or dependencies. Domain workstreams (identity, policy, services/addressing, compute/device, access plane) run inside the later phases and can be sequenced or parallelized according to organizational priorities.

2. Guiding Constraints

  • Changes originate from a designated authoritative source and close with provenance.
  • Elevated privilege is time-bounded and scoped (just-in-time).
  • Derived copies and subordinate systems remain explicitly non-authoritative.
  • Drift between intended and observed state is classified and visible.
  • No full rip-and-replace is required to make progress.

3. Phases

Phase 0 — Charter and Alignment

Objective: Confirm scope, stakeholders, success criteria, and decision rights.

Key activities - Review and finalize the Project Charter. - Identify sponsor, project lead, and domain leads. - Confirm in-scope domains and any organizational constraints (data residency, existing tools, timeline pressure). - Agree on the evidence and provenance expectations that will apply to all later changes.

Deliverables - Signed or accepted Project Charter. - Stakeholder and role list. - Initial risk register.

Supporting material - Why Modernization Is Hard — leadership framing of the problem - Principles — the rules the charter commits to - Chapter 00 — The Problem Nobody Talks About - Chapter 10 — Leadership Takeaway

Exit criteria - Leadership can state the problem, the target outcome, and how success will be measured.

Phase 1 — Current-State Assessment

Objective: Make the existing governance model and hidden dependencies explicit.

Key activities - Inventory major directory and identity dependencies (organizational structure, delegation, policy, service accounts, certificates, naming, addressing). - Document how structure and authority are currently encoded (hierarchical containers, group membership, policy inheritance, etc.). - Identify sources of truth (or competing sources) for human and non-human identity lifecycle events. - Capture known fragmentation points and reconciliation pain. - Produce a dependency and risk map that highlights migration hazards.

Deliverables - Current-state assessment report. - Dependency and hidden-surface inventory. - List of candidate authoritative origins for key object classes. - Initial normalization recommendations (what must be cleaned or rationalized before migration).

Supporting material - Read-Only AD Assessment Guide — discovery without changing the directory - Chapter 02 — Analyzing the Client/Server Estate - Identity and Directory Transformation Inventory - GPO-to-Cloud Governance Gaps - Old AD vs New Entra ID — reference for the assessment team

Exit criteria - The team can describe, in concrete terms, what the directory currently “knows” about the organization and what would break if that knowledge disappeared.

Phase 2 — Target Architecture Definition

Objective: Define the attribute-oriented structure and control-plane model that will replace implicit hierarchy.

Key activities - Specify the attributes that will represent organizational position, lifecycle, and security context. - Define how dynamic membership and scoped policy will be driven from those attributes. - Describe the layered model (Identity → Structure → Policy → Governance) and the role of each layer. - Identify control planes (identity, addressing, policy, telemetry, etc.) and their boundaries. - State the rules for authoritative origin versus derived/subordinate copies. - Document the drift classes that will be monitored (schema, semantic, provenance, authorization, identity, and contention on the authoritative source).

Deliverables - Target architecture description (conceptual, not implementation-specific). - Attribute model and mapping guidance from current structures. - Control-plane diagram or narrative. - Drift taxonomy and detection approach outline. - Provenance and evidence expectations for changes.

Supporting material - Single Source of Truth - From Attributes to Access (dynamic groups) - Delegation Matrix - Change Control and Provenance - Architecture Series

Exit criteria - Domain leads can explain how a given organizational fact will be expressed, how policy will attach to it, and how drift will be detected, without relying on internal decision-record numbers.

Phase 3 — Domain Playbooks and Wave Planning

Objective: Produce executable playbooks for each in-scope domain and sequence them into waves.

Key activities - For each domain (identity structure, policy, services/addressing, compute/device, access plane): - Define objectives and success measures. - Map current constructs to target constructs. - Identify bridging or coexistence patterns. - Specify entry criteria, exit criteria, and rollback conditions. - Define the evidence that must be produced for each change. - Sequence the domains into waves that respect dependencies (structure before policy, identity before compute, etc.). - Identify any organization-specific constraints that affect sequencing.

Deliverables - Domain playbooks (one per major domain). - Wave plan with sequencing, gates, and rollback triggers. - Evidence checklist applicable to every wave.

Supporting material - Chapter 03 — Analysis → Plan → Delivery - Chapters 04–08 — identity, policy, services, compute and access playbooks - GPO Sunset Program and GPO Parse and Crosswalk - Conditional Access Policy Library - Intune + Azure Arc Modernization - DNS Modernization Guide and PKI Modernization Guide - Test Plans — evidence checklist inputs

Exit criteria - At least the first wave has a complete playbook that a team could execute with existing tools and processes.

Phase 4 — Pilot / First Wave Execution

Objective: Execute a controlled first wave and validate the change-control and evidence pattern.

Key activities - Select a limited, representative scope for the first wave (recommended: identity structure and dynamic membership for a subset of the organization). - Originate the changes from the designated authoritative source. - Execute under least-privilege / just-in-time elevation. - Close each change with provenance and collect the required evidence. - Detect and classify any drift that appears during or after the wave. - Conduct a lessons-learned review.

Deliverables - Executed first-wave changes with provenance records. - Evidence package. - Drift findings (if any) and remediation notes. - Updated playbooks and wave plan based on lessons learned.

Supporting material - Chapter 09 — Migration Roadmap: Phased Plan, Gates, Rollback - PIM Self-Request with Approval — just-in-time elevation for wave execution - HR-Driven Identity — originating changes from the authoritative source - End User Training Guide

Exit criteria - The organization has demonstrated that a change can originate from the authoritative source, execute under controlled privilege, close with provenance, and be validated against the intended state.

Phase 5 — Progressive Rollout and Steady-State Governance

Objective: Extend the pattern across remaining domains and establish ongoing drift detection and evidence practices.

Key activities - Execute subsequent waves according to the updated plan. - Expand the attribute model and dynamic constructs as additional domains are brought under the target architecture. - Stand up or refine continuous drift detection against the authoritative origin. - Transition from project-mode change control to steady-state operational governance. - Capture residual risks and any items that remain outside the modernization scope.

Deliverables - Completed domain transformations (or documented residual scope). - Operational drift detection and evidence process. - Final project report with outcomes against success criteria. - Recommendations for ongoing ownership.

Supporting material - Continuous Monitoring Strategy - Gap Closure Register - Training Program and Education Program

Exit criteria - Success criteria from the charter are met or explicitly deferred with rationale. - Ownership for the authoritative origin and drift detection has transferred to steady-state operations.

4. Domain Workstreams (Summary)

Domain Primary Focus Typical Dependencies Suggested Position Detailed project
Identity structure Attribute model, dynamic membership, lifecycle origin Assessment complete Early (Wave 1) Identity Lifecycle & Provisioning
Policy Mapping of existing policy to attribute-driven scope Identity structure After identity Playbooks: GPO Sunset Program, Conditional Access Policy Library
Services / Addressing Naming, IP management, related dependencies Assessment; may bridge Parallel or mid Network & Access Modernization
Compute / Device Device identity and management alignment Identity structure Mid to late Endpoint & Device Modernization
Access plane Token-based / application-aware access patterns Identity and policy Later Network & Access Modernization

Further detailed projects that run alongside these workstreams: Privileged Access & Administrative Identity, Data Platform Identity Transformation, Continuous Monitoring & Evidence Fabric, and Supply Chain & Software Bill of Materials. Each has a charter and a plan; see Complementary Modernization Projects.

5. Governance and Decision Rights

  • Sponsor approves scope changes, major sequencing shifts, and acceptance of residual risk.
  • Project lead owns the overall plan, wave sequencing, and cross-domain dependencies.
  • Domain leads own playbook content, execution readiness, and domain-specific evidence.
  • All material changes to the target architecture or authoritative-origin rules require project-lead and sponsor concurrence.

6. Risks and Mitigations (Selected)

Risk Mitigation
Incomplete discovery of hidden dependencies Structured assessment checklist; pilot wave designed to surface unknowns early
Competing sources of truth persist Explicit designation of authoritative origin per object class; drift class for contention
Organizational resistance to making authority explicit Early stakeholder alignment; pilot that demonstrates controlled rather than disruptive change
Tooling leads the design Target architecture and change-control pattern defined before tool selection or configuration
Physics / residency limits on centralization Logical centralization of truth; physical distribution of subordinate copies only

7. Success Measures (Project Level)

  • Current-state assessment completed and accepted.
  • Target architecture documented and understood by domain leads.
  • First wave executed with full provenance and evidence.
  • Drift detection approach operational for the domains in scope.
  • Residual risks documented and ownership assigned.
  • Leadership can describe the modernization path and outcomes without reference to internal technical decision records.

8. Immediate Next Actions

  1. Review and accept this plan against the Project Charter.
  2. Confirm Phase 0 stakeholders and decision rights.
  3. Scope the Phase 1 assessment (data sources, access, timeline).
  4. Identify the candidate authoritative origin(s) for human identity lifecycle events.
  5. Draft the outline of the target attribute model.

This plan is a project artifact. It incorporates the modernization concepts of authoritative origin, attribute-driven structure, explicit drift, and controlled evidence-producing change. It contains no internal architectural decision record identifiers or substrate-specific document numbers.