Chapter 09 — Design, Pilot and Rollout

The program-level view of Phases 1 to 3 and gates G1 to G3: turning the approved plans into designs and a working foundation, proving the whole pattern on a pilot, and rolling it out in waves scoped by attribute values, with each gate’s criteria.

Design from the plans, prove the design on people who can tolerate a bad day, then repeat what worked until there is no one left to move.

NoteIn this chapter

Book 01’s Phases 1 to 3 as the program office runs them. Phase 1, Foundation, turns the approved plans into designs and blueprints and builds the shared foundation they need, ending at gate G1. Phase 2, the pilot, proves the full pattern on one division against measured success criteria, with a rollback for every surface, ending at G2. Phase 3, general rollout, scales it in waves defined by attribute values rather than by OUs, ending at G3. For each phase: the milestones, the corrections this book makes to the master plan, and the gate checklist. The working detail stays in the domain books, which are linked throughout.

From approved plans to a moving estate

Pre-flight ends with a committed assessment and no open priority-one findings (Chapter 08). Phase 1 opens by generating the eight modernization plans from it and approving them, the last two steps of that chapter’s assessment sequence. The next three phases of Book 01’s roadmap are where the estate starts to move:

Phases 1 to 3 and their master plan sources
Book 01 phase and gate Master plan source What the phase delivers
Phase 1, Foundation → G1 Foundation Complete The end of Phase 1, Assessment (plan generation and approval, M-011 and M-012, and pre-pilot preparation, M-013), and Phase 2, Planning and Design (M-014 to M-021) Approved plans and designs; enterprise groups, administrative units and the Conditional Access baseline; the HR feed; Cloud PKI, the DNS resolver and Arc ready for the pilot
Phase 2, Pilot division → G2 Pilot Clean Phase 3, Pilot (M-022 to M-031) The whole pattern working on one division, measured against success criteria
Phase 3, General rollout → G3 Rollout Complete Phase 4, Scale (M-032 to M-037) Every remaining division moved, in waves

Book 01’s illustrative calendar gives these phases weeks 5 to 36; the master plan’s runs from week 9 to week 33. Both are sequencing models. The five workstreams (identity, policy, services, compute and access) run in parallel through all three phases, and the gates follow the dependency chain (Book 01, Chapter 12).

A vertical flow of six boxes. A violet box at the top: the committed assessment, from gate G0. A blue box: Phase 1, Foundation, plans generated and approved, designs approved, groups, administrative units, the Conditional Access baseline and the HR feed. An amber gate box: G1, Foundation Complete, decided by the steward, foundation drift-clean, baseline Conditional Access enforced, High findings closed. A blue box: Phase 2, Pilot division, the whole pattern on one division, measured against success criteria. An amber gate box: G2, Pilot Clean, co-signed by the steward and the executive sponsor, a zero-drift hold, no hybrid-joined device without a cut date, success criteria met. A blue box: Phase 3, General rollout, waves by attribute value, two or three divisions at a time. A green gate box: G3, Rollout Complete, decided by the executive sponsor with the steering committee, every division through its exit gate. Arrows join each box to the next.
Figure 1: Phases 1 to 3 and the gates between them: design and build the foundation, prove the pattern on one division, then roll it out in waves, each gate evaluated from repository and drift data.

Phase 1 — Foundation

Phase 1 opens with the eight plans: generated from the committed assessment, reviewed by the workstream leads and the security lead, and approved by the steward, with the steering committee reviewing the combined set (Chapter 08, steps 4 and 5). Then it has two halves that run together: designing every surface from the approved plans, and building the shared primitives the pilot needs. The master plan treated the second half as the last week of assessment, but it creates objects in the target tenant, so it belongs here.

Design milestones

Phase 1 design milestones (master plan M-014 to M-021)
ID Milestone Deliverable Owner
M-014 Attribute taxonomy finalized Attribute dimensions mapped to slots, canonical value lists, validation and governance rules, committed as AttributeTaxonomy.json with status APPROVED Identity lead
M-015 Dynamic group design complete Rules for every dimension combination the waves use, tested in a non-production tenant, with a naming convention and lifecycle Endpoint lead
M-016 Intune policy design complete Every GPO intent mapped to settings catalog, endpoint security or imported ADMX; intents with no equivalent decided and recorded; profiles and compliance policies exported under plans/intune/ Endpoint lead
M-017 Conditional Access design The policy set designed and running in report-only mode for at least seven days, with impact analysis, exceptions and emergency access accounts documented Security lead
M-018 Sync design Scope filtering, attribute flow (including the extension attributes), sign-in method and a safe first-sync plan documented Identity lead
M-019 DNS Private Resolver design Hub-and-spoke topology, forwarding rulesets, split-brain patterns and resolution-failure monitoring documented DNS lead
M-020 Cloud PKI design complete Root of trust decided (Cloud PKI root or bring-your-own CA) and recorded as a decision; template migration matrix; SCEP profile and certificate-based authentication binding designs; lifecycle procedures PKI lead
M-021 Design review approved Every design approved by the steward and reviewed by the steering committee Steward

M-017 (Conditional Access) and M-019 (DNS) run in parallel with the attribute, group and Intune track (M-014 to M-016), which is the critical path. M-020 runs in parallel too, but needs the security assessment’s escalation findings, and PKI always follows identity: certificate-based authentication can’t be validated until the user and device objects it binds to are synced and mapped.

The attribute taxonomy

Everything the waves do is scoped by attributes, so M-014 comes first. The master plan names five dimensions, Region, Site, Department, Role and Environment, and maps them onto extensionAttribute1 to 15. The workbook already has one assignment of those slots for the whole site, the program attribute map in Book 03, Chapter 06, and the taxonomy uses it rather than choosing slots locally:

The master plan’s dimensions in the program attribute map
Master plan dimension User object Device object
Region extensionAttribute4, region code extensionAttribute1, region
Department extensionAttribute6, division code, and extensionAttribute10, organization code extensionAttribute3, department or function
Role extensionAttribute12, position category extensionAttribute12, device role
Environment — extensionAttribute13, environment
Site No slot assigned No slot assigned

Two things follow. Site has no slot. A program that waves by site either uses a native location property that membership rules can already read, or asks the map’s owner for a reserved slot; it doesn’t take one locally. The OU tree isn’t the authority. The master plan derived dimension values from the OU hierarchy. The OU analysis is a good seed for the crosswalk and for the transition, but each user value has one designated source, normally HR through the provisioning feed, and each slot has one writer (Book 03, Chapter 06). Microsoft’s own guidance points the same way: a dynamic group is only as secure as the write permissions on the attributes its rule reads, in Entra ID and in any source directory.1

The two object types are written differently. For synced users, extensionAttribute1 to 15 flow from Active Directory, and both Microsoft sync engines carry them.2 Device extension attributes are set on the Entra ID device object through Microsoft Graph, and a device rule can use them only once they are written there.34

Dynamic groups, policy and access

Dynamic groups (M-015). Dynamic membership groups need Microsoft Entra ID P1 for each unique user who is a member of one; device-based groups need no license.5 The master plan required group processing to finish within fifteen minutes. Microsoft doesn’t offer that: membership changes are usually processed within a few hours and can take more than 24, depending on the number of groups, the number of changes and the complexity of the rules.6 So the design measures processing time in the non-production tenant and plans each wave around hours, not minutes. Rules that use -match or -contains are slower and are kept out of wave groups where possible.7 Rules don’t use the memberOf operator at all: Microsoft ended its preview on November 3, 2026, and rules that still use it have stopped updating (Book 02, Chapter 09).

Intune policy (M-016). The GPO plan’s intents become Intune profiles. Intune’s Group Policy analytics imports GPO reports, shows which settings have an MDM equivalent and can create a settings catalog policy from the supported ones.8 The intents with no equivalent get a recorded decision (a custom OMA-URI, an accepted gap, or a different control) in the GPO sunset program (Book 05, Chapter 07), and the working policy set is Book 05, Chapter 08.

Conditional Access (M-017). The master plan called for “15+” policies. The program’s library is now one numbered set in Book 04, Chapter 07, enforced in five waves, and Phase 1 enforces its foundation wave and the baseline. Report-only mode evaluates a policy and logs the result without enforcing it,9 and Microsoft recommends at least a week in report-only before enforcement,10 which matches the master plan’s seven days. Seven days is the gate minimum (M-017 and G1); the plan in Book 02 and the guides is two to four weeks in report-only, so a policy that meets the minimum earlier can move on, and one with unresolved impact stays. Emergency access accounts are designed here too: Microsoft’s guidance is at least two cloud-only accounts, and the program standard is two, with phishing-resistant methods, excluded from every policy that blocks or restricts sign-in, monitored on every use and validated at least every 90 days.11

Sync (M-018). The master plan assumed Microsoft Entra Connect Sync with staging mode. Microsoft now describes Cloud Sync as its strategic direction and the recommended path for most organizations,12 and Book 02, Chapter 09 sets the program’s rule: Cloud Sync unless a forest needs something only Connect Sync does. Password hash sync is the program’s sign-in method either way. Staging mode is a Connect Sync feature; Cloud Sync gets its resilience from multiple active agents, so the first-sync plan names which engine it is written for.

DNS (M-019). Azure DNS Private Resolver has an inbound endpoint that on-premises conditional forwarders target to resolve Azure private zones, and an outbound endpoint whose forwarding rulesets send Azure queries for on-premises names to the domain’s DNS servers. Each endpoint needs its own dedicated subnet, and a ruleset holds up to 1,000 rules.13 The coexistence design and split-brain rules are Book 08, Chapters 02 and 10.

Cloud PKI (M-020). Cloud PKI offers two models: a root and issuing CAs in the cloud, or an issuing CA in the cloud anchored to your own private root (bring your own CA).14 Three facts bound the design: it issues leaf certificates only through SCEP to Intune-enrolled devices, a tenant can hold at most three CAs, counting roots, issuing CAs and BYOCA issuing CAs together, and CRLs are valid for seven days.15 Server certificates, including domain controller and LDAPS certificates, stay on AD CS (Book 07, Chapters 04 and 07).

Foundation build and pre-pilot readiness

While the designs are reviewed, the shared foundation is built. Book 01 sets the content: enterprise dynamic groups, administrative units for Tier 1 and selected Tier 2 scopes, the HR-to-cloud provisioning feed for the foundation scope (Book 03, Chapter 12), the enterprise Conditional Access baseline, IP address management for Tier 0 infrastructure, Arc for the platform host and the pilot servers, and single sign-on with FIDO2 security keys and passkeys open to Tier 0 administrators. The master plan’s pre-pilot week (M-013) adds the pilot-specific readiness:

  • Pilot selection. Pilot scope defined (see Phase 2) and attribute-based dynamic groups built and validated for it.
  • High findings. Remediation of every High finding from the security assessment, verified by re-scan. This is the master plan’s “before Phase 3” deadline, which is Book 01’s pilot.
  • Intune staged. Pilot configuration profiles and compliance policies created from the GPO plan and held back from enforcement until the pilot opens.
  • Conditional Access. The pilot policies running in report-only mode against pilot users, with sign-in logs reviewed.
  • Cloud PKI. The root or BYOCA issuing CA created and the first SCEP profile drafted for the pilot certificate.
  • DNS. The Private Resolver deployed in the hub network with forwarding rulesets for the AD zones, and no conditional-forwarder changes on-premises yet.

Gate G1 — Foundation Complete

The steward decides G1 (Book 01, Chapter 09). The checklist combines Book 01’s criteria with the master plan’s design and pre-pilot milestones:

Phase 2 — The pilot

The pilot proves the complete pattern, identity, devices, DNS, PKI and server management, on real people before anything scales.

Scope

Book 01 sets the pilot’s scope as one division, typically IT, which tolerates disruption best. The master plan sized its pilot by surface instead:

The master plan’s pilot sizes, used as a floor
Surface Pilot scope Selection criteria
Devices 50 to 100 devices across 2 or 3 sites Laptops and desktops on supported Windows, with representative attribute values
Identity 20 to 50 users across 3 or 4 departments Standard users, power users and 2 or 3 pilot administrators
Servers 2 or 3 servers for Arc Non-critical tier, representative OS versions
PKI 1 or 2 certificate use cases Wi-Fi authentication and VPN certificates
DNS Pilot sites only Sites with both on-premises and Azure workloads

The two fit together: the division is the scope, and the master plan’s sizes are a floor for what the pilot must exercise. If the pilot division can’t supply them (it sits at one site, say, or has no non-IT users), add a small group of willing volunteers from other departments so that the pilot covers representative attribute values. The source’s device mix included Windows 10, which reached end of support on October 14, 2025.16 Intune now treats Windows 10 as an “allowed” version whose functionality isn’t guaranteed,17 so the pilot targets Windows 11, and any Windows 10 device in it is a documented exception.

Milestones

Phase 2 pilot milestones (master plan M-022 to M-031)
ID Milestone Deliverable Owner
M-022 Sync deployed Sync running with password hash sync; the first sync validated; pilot users synced Identity lead
M-023 Pilot devices joined Pilot devices registered with attributes populated in Entra ID: new devices Entra joined, existing ones reset and re-enrolled, or hybrid joined with a cut date Endpoint lead
M-024 Intune policies assigned GPO-equivalent policies deployed through attribute-based dynamic groups Endpoint lead
M-025 Conditional Access enforced for the pilot MFA, device compliance and authentication strength policies active Security lead
M-026 PIM for privileged roles Every pilot administrator eligible, not permanent; no permanent Global Administrator except the emergency access accounts Identity lead
M-027 Hybrid DNS validated On-premises to Azure and Azure to on-premises resolution confirmed at pilot sites DNS lead
M-028 Cloud PKI certificates issued SCEP profiles deployed; Wi-Fi and VPN authentication verified with Cloud PKI certificates PKI lead
M-029 Certificate-based authentication validated Certificate sign-in working for pilot users through staged rollout PKI lead
M-030 Pilot servers under Arc Machine configuration applied; Azure Policy compliance confirmed Infrastructure lead
M-031 Pilot success criteria met Every criterion in the table below at or above target Project manager

Three corrections apply. Permanent Global Administrators. The master plan wanted “zero permanent Global Admins.” Microsoft’s guidance is the opposite for one case: emergency access accounts hold Global Administrator as a permanent active assignment, not an eligible one.18 Every other privileged assignment is eligible through PIM. Staged rollout is temporary. Microsoft supports staged rollout for certificate-based authentication to test a few groups before converting a federated domain to managed authentication, but it isn’t meant to be a permanent mixed state, and the domain cutover is still a separate step.19 Hybrid join is a waypoint. Every hybrid-joined pilot device carries a cut date (Book 05, Chapter 02).

M-026 is wider than the privileged-access project’s pilot. That project’s pilot-scale criterion is just-in-time elevation for at least one high-risk role class (Chapter 06; Book 04, Chapter 02). M-026 asks for more: every privileged role a pilot administrator holds is eligible, not permanent. The two don’t conflict. The project’s criterion is the floor, proved on its first role class; M-026 is what the program’s G2 checks, so the pilot exercises the whole pattern on real administrators before the rollout carries it to everyone else.

Pilot success criteria

The master plan measured the pilot against eight criteria, each with a target and a failure threshold. The values are illustrative; set them in the program’s decision log before the pilot opens, and evaluate them from the systems named, not from opinion.

Pilot success criteria
Criterion Target Measurement Fails below or above
Device enrollment success rate Above 98% Intune enrollment report Below 95%
Policy compliance rate Above 95% Intune compliance dashboard Below 90%
Authentication success rate Above 99% Entra sign-in logs Below 97%
Certificate issuance success Above 95% Intune certificate report Below 90%
DNS resolution success Above 99.5% Synthetic and organic monitoring queries Below 99%
User satisfaction (survey) Above 80% positive Pilot user survey Below 70%
Help desk ticket volume Below 5% of pilot users Ticket tracking system Above 10%
Mean time to compliance Under 4 hours Intune reporting Over 24 hours

The source’s summary milestone said “zero auth failures,” which contradicts its own 99 percent target; the table governs. A mid-pilot check-in, the master plan’s mitigation for a poor survey result, comes halfway through so that concerns are fixed before the final survey.

Rollback, surface by surface

Every surface in the pilot has a rollback trigger and a procedure, and Book 01’s program-level triggers (drift above threshold, Conditional Access blocking legitimate sign-ins, drift detection going silent) sit above them (Book 01, Chapter 12).

Pilot rollback procedures
Surface Rollback trigger Procedure Recovery time
Identity (sync) Sync corruption, duplicate objects, authentication failures Stop the sync schedule; for Connect Sync, promote the staging-mode server; for Cloud Sync, revert the configuration change; keep directory sign-in to the platform host available Under 2 hours
Devices (Intune) Policy conflict locks devices out, or compliance failures above 10% Unassign the profiles from the pilot group; for domain-joined and hybrid-joined devices, re-enable the GPO links on the pilot OUs Under 4 hours
Conditional Access Legitimate users blocked; emergency access needed repeatedly Switch the pilot policies back to report-only; never delete them Under 30 minutes
DNS Resolution failures above 1%; SRV lookup failures Revert the conditional-forwarder changes on-premises; disable the resolver’s forwarding rules; check for records a rollback can delete in Azure private zones (Book 08, Chapter 10) Under 1 hour
PKI (Cloud PKI) Issuance failures, or authentication failures with the new certificates Remove the SCEP profiles from the pilot group; for domain-joined devices, re-enable AD CS autoenrollment for the pilot templates Under 4 hours
Servers (Arc) Agent degrades performance or conflicts with policy Disconnect the server, which deletes its Arc resource; the Connected Machine agent can stay installed20 Under 1 hour

Gate G2 — Pilot Clean

G2 is signed jointly by the steward and the executive sponsor, one of three joint gates with G3 and G5 (Book 01, Chapter 09).

Phase 3 — General rollout

Phase 3 repeats the proven pattern until every division has moved. It is the longest phase.

Waves defined by attribute values

The master plan scaled in four waves, each about a quarter of the estate and three weeks long, organized by the attribute dimensions Region, then Site, then Department. Book 01 rolls out division by division, two or three at a time, two or three weeks each. The two are the same method seen from different heights. A wave is a set of divisions chosen by attribute value, usually by region, and inside a wave each division follows the same sub-pattern: plan, in-division pilot, full availability, drift-clean hold, and a weekly green, yellow or red report. Because waves are defined by attribute values rather than by OUs, the scope of each wave is a query on the authoritative source, and the dynamic groups that target it already exist from Phase 1.

Each of the migration’s four tracks selects its wave members from its own source of truth. Users are selected by their HR-sourced attributes and devices by the attributes provisioning writes on the device object, so a region’s people and their workstations can move in the same wave without one reading the other. Servers are selected by Azure resource group and tag once they’re Arc-enabled. Non-person identities move with their owning application, so a service account joins the wave of the application that owns it, not the wave of the division it once sat in.

A left-to-right flow. A slate box on the left: the program attribute map, with region, division and organization codes on users and region, department and role on devices. It feeds four stacked blue wave boxes: wave 1, the lowest-risk region, about a quarter of the estate; wave 2, the second region, about half cumulatively; wave 3, the third region, about three quarters; wave 4, all remaining, all of the estate. Each wave points to an amber box listing the per-division sub-pattern: plan, in-division pilot, full availability, drift-clean hold, weekly status. That box points to a green box: G3, Rollout Complete.
Figure 2: Waves are defined by attribute value: each wave is a set of divisions selected by region, the lowest-risk first, and every division in a wave follows the same sub-pattern before the wave closes.

The master plan’s scaling rules carry over unchanged:

  • Waves start with the lowest-risk region and move toward more complex environments.
  • Every wave passes the same validation the pilot did, against the same success criteria.
  • Drift detection runs daily against the migrated scope from the first wave.
  • GPO links stay in place during a wave; each is then disabled and, only after seven days of clean compliance, removed from the migrated OU; the GPO objects themselves are retired in Phase 4 (Book 05, Chapter 07).

Book 05 also talks about waves, but its waves are by workload, not by division: compliance, Endpoint Protection, device configuration, then Windows Update, each moved from Configuration Manager to Intune on co-managed devices. The two fit together. The division waves here decide which devices move; inside them, Book 05 uses each division wave as the next ring for every workload (Book 05, Chapter 08).

Milestones

Phase 3 rollout milestones (master plan M-032 to M-037)
ID Milestone Scope Owner
M-032 Wave 1 complete (first region) About 25% of devices, users and servers All leads
M-033 Wave 2 complete (second region) About 50% cumulative All leads
M-034 Wave 3 complete (third region) About 75% cumulative All leads
M-035 Wave 4 complete (all remaining) 100% moved, or recorded as a documented exception All leads
M-036 GPO links removed from migrated OUs No GPO links remain on migrated OUs Endpoint lead
M-037 Dynamic groups populated and validated Attribute coverage at 100% for every in-scope object Identity lead

Scaling risks

Scale exposes what a pilot can’t. The master plan’s risk table for this phase, with its mitigations and contingencies:

Phase 3 scaling risks
Risk Impact Mitigation Contingency
A wave exposes applications the pilot didn’t see Authentication failures, business disruption Application discovery before each wave; Conditional Access in report-only for at least a week before enforcement, as for the pilot21 Exclude the application through a governed exception policy
GPO-to-Intune gaps appear at scale Configuration drift, compliance failures Keep GPO links during the wave; disable, then remove, a link only after seven days of clean compliance Re-enable GPO for the affected OUs; record the gap
Dynamic group processing slows at high user counts Policy assignment delays, enrollment gaps Stagger attribute writes; monitor processing time; plan in hours Convert critical policies to assigned groups for the wave
Mass certificate issuance strains Cloud PKI Issuance failures, Wi-Fi and VPN disruption Stagger SCEP profile deployment across the wave; monitor issuance Throttle enrollment; extend the wave
Split-brain DNS inconsistencies across many sites Name resolution failures for hybrid resources Monitoring probes at each site; forward and reverse tests Revert specific forwarding rules; keep AD DNS for affected zones
User resistance grows with scale Help desk spikes, negative sentiment Communications before each wave, training, department champions Pause the wave; add training and support
Key people unavailable during a wave Delay, knowledge gaps Cross-train two people per workstream; every procedure in the repository Shift the wave; activate backups

Two of these rest on facts worth checking before the wave, not after. Dynamic group processing can take more than 24 hours under a large volume of attribute changes,22 so staggering attribute writes is a schedule input, not a nicety. Microsoft doesn’t publish a Cloud PKI issuance rate limit that the program could plan against, so the certificate risk is the program’s own judgment; measure issuance in the pilot and size the stagger from that.

Gate G3 — Rollout Complete

The executive sponsor decides G3 with the steering committee (Book 01, Chapter 09).

After G3 the estate runs on the target, and what remains is retiring what it ran on before: Phases 4 and 5, Legacy retirement and AD DS retirement, in Chapter 10.

Key takeaways

  1. Phase 1 designs every surface from the approved plans and builds the shared foundation; G1 needs the baseline enforced, the HR feed live and every High finding closed.
  2. Attribute dimensions come from the program attribute map, with authority from HR and one writer per slot, not from the OU tree.
  3. The pilot is one division, topped up to the master plan’s sizes where needed, measured against eight numeric criteria with a rollback for every surface.
  4. Rollout waves are sets of divisions chosen by attribute value, and dynamic groups are planned in hours, not minutes.
  5. The steward alone clears G0, G1 and G4. G2, G3 and G5 are joint: steward and executive sponsor; sponsor and steering committee; sponsor and CIO.

  1. Microsoft Learn, “Manage rules for dynamic membership groups in Microsoft Entra ID” (extension attributes 1 to 15 in rules; device extension attributes must be set on the device; security consideration on attribute write permissions; license requirements), https://learn.microsoft.com/entra/identity/users/groups-dynamic-membership (accessed Oct 21, 2026).↩︎

  2. Microsoft Learn, “Migrate from Microsoft Entra Connect to Cloud Sync: Decision Guide” (Cloud Sync as the strategic direction and recommended path for most organizations; directory extensions 1 to 15 supported by both engines), https://learn.microsoft.com/entra/identity/hybrid/cloud-sync/connect-to-cloud-sync-decision-guide (accessed Oct 21, 2026).↩︎

  3. Microsoft Learn, “Manage rules for dynamic membership groups in Microsoft Entra ID” (extension attributes 1 to 15 in rules; device extension attributes must be set on the device; security consideration on attribute write permissions; license requirements), https://learn.microsoft.com/entra/identity/users/groups-dynamic-membership (accessed Oct 21, 2026).↩︎

  4. Microsoft Graph, “Update device,” Example 2, “Write extensionAttributes on a device,” https://learn.microsoft.com/graph/api/device-update?view=graph-rest-1.0 (accessed Oct 21, 2026).↩︎

  5. Microsoft Learn, “Manage rules for dynamic membership groups in Microsoft Entra ID” (extension attributes 1 to 15 in rules; device extension attributes must be set on the device; security consideration on attribute write permissions; license requirements), https://learn.microsoft.com/entra/identity/users/groups-dynamic-membership (accessed Oct 21, 2026).↩︎

  6. Microsoft Learn, “Understand and manage dynamic group processing in Microsoft Entra ID” (typically within a few hours; can take more than 24 hours; factors include the number of groups, the number of object changes and rule operators such as Match, Contains and memberOf), https://learn.microsoft.com/entra/identity/users/manage-dynamic-group (accessed Oct 21, 2026).↩︎

  7. Microsoft Learn, “Understand and manage dynamic group processing in Microsoft Entra ID” (typically within a few hours; can take more than 24 hours; factors include the number of groups, the number of object changes and rule operators such as Match, Contains and memberOf), https://learn.microsoft.com/entra/identity/users/manage-dynamic-group (accessed Oct 21, 2026).↩︎

  8. Microsoft Learn, “Create a Settings Catalog policy using your imported GPOs in Microsoft Intune,” https://learn.microsoft.com/intune/device-configuration/migrate-group-policy, and “Import and analyze your on-premises GPOs using Group Policy analytics in Microsoft Intune,” https://learn.microsoft.com/intune/device-configuration/import-group-policy-analytics (both accessed Oct 21, 2026).↩︎

  9. Microsoft Learn, “Analyze Conditional Access policy impact” (report-only mode evaluates policies without enforcing them; results are logged in the sign-in logs), https://learn.microsoft.com/entra/identity/conditional-access/concept-conditional-access-report-only (accessed Oct 21, 2026).↩︎

  10. Microsoft Learn, “Plan a Conditional Access deployment” (“Enable each policy in report-only mode for at least one week before enforcement”), https://learn.microsoft.com/entra/identity/conditional-access/plan-conditional-access#deploy-conditional-access-policies (accessed Oct 21, 2026).↩︎

  11. Microsoft Learn, “Manage emergency access accounts in Microsoft Entra ID,” Security guardrails summary (at least two cloud-only accounts; phishing-resistant methods; Global Administrator as permanent active, not eligible; excluded from policies that block or restrict sign-in; validated at least every 90 days), https://learn.microsoft.com/entra/identity/role-based-access-control/security-emergency-access (accessed Oct 21, 2026).↩︎

  12. Microsoft Learn, “Migrate from Microsoft Entra Connect to Cloud Sync: Decision Guide” (Cloud Sync as the strategic direction and recommended path for most organizations; directory extensions 1 to 15 supported by both engines), https://learn.microsoft.com/entra/identity/hybrid/cloud-sync/connect-to-cloud-sync-decision-guide (accessed Oct 21, 2026).↩︎

  13. Microsoft Learn, “What is Azure DNS Private Resolver?” (inbound and outbound endpoints, each on a dedicated delegated subnet; DNS forwarding rulesets of up to 1,000 rules), https://learn.microsoft.com/azure/dns/dns-private-resolver-overview (accessed Oct 21, 2026).↩︎

  14. Microsoft Learn, “Microsoft Cloud PKI deployment for Microsoft Intune” (Cloud PKI root CA or bring your own CA), https://learn.microsoft.com/intune/cloud-pki/deployment-models (accessed Oct 21, 2026).↩︎

  15. Microsoft Learn, “Overview of Microsoft Cloud PKI for Microsoft Intune,” Overview of features (SCEP leaf issuance to Intune MDM-enrolled devices; CRL valid seven days) and Known issues and limitations (up to three CAs per tenant, counting root, issuing and BYOCA issuing CAs), https://learn.microsoft.com/intune/cloud-pki/ (accessed Oct 21, 2026).↩︎

  16. Microsoft Learn, “Windows 10 reaching end of support” (October 14, 2025), https://learn.microsoft.com/lifecycle/announcements/windows-10-end-of-support (accessed Oct 21, 2026).↩︎

  17. Microsoft Learn, “Supported operating systems and browsers in Intune” (Windows 10 is an allowed version after end of support; Windows client editions listed, no Windows Server), https://learn.microsoft.com/intune/fundamentals/ref-supported-platforms (accessed Oct 21, 2026).↩︎

  18. Microsoft Learn, “Manage emergency access accounts in Microsoft Entra ID,” Security guardrails summary (at least two cloud-only accounts; phishing-resistant methods; Global Administrator as permanent active, not eligible; excluded from policies that block or restrict sign-in; validated at least every 90 days), https://learn.microsoft.com/entra/identity/role-based-access-control/security-emergency-access (accessed Oct 21, 2026).↩︎

  19. Microsoft Learn, “Migrate to cloud authentication using Staged Rollout” (certificate-based authentication is a staged rollout option; staged rollout isn’t designed to be permanent; the domain cutover is separate), https://learn.microsoft.com/entra/identity/hybrid/connect/how-to-connect-staged-rollout (accessed Oct 21, 2026).↩︎

  20. Microsoft Learn, “How to rename Azure Arc-enabled servers and migrate across regions,” Disconnect from Azure Arc (azcmagent disconnect deletes the machine resource and doesn’t remove the Connected Machine agent), https://learn.microsoft.com/azure/azure-arc/servers/manage-howto-migrate (accessed Oct 21, 2026).↩︎

  21. Microsoft Learn, “Plan a Conditional Access deployment” (“Enable each policy in report-only mode for at least one week before enforcement”), https://learn.microsoft.com/entra/identity/conditional-access/plan-conditional-access#deploy-conditional-access-policies (accessed Oct 21, 2026).↩︎

  22. Microsoft Learn, “Understand and manage dynamic group processing in Microsoft Entra ID” (typically within a few hours; can take more than 24 hours; factors include the number of groups, the number of object changes and rule operators such as Match, Contains and memberOf), https://learn.microsoft.com/entra/identity/users/manage-dynamic-group (accessed Oct 21, 2026).↩︎

Back to top