Project plan · Sample · Project

Attribute-Driven Migration: The Cross-Track Attribute Foundation

A sample project plan for the attribute foundation the HR, Intune, Arc and non-person identity tracks share: one schema, one writer per attribute, attributes proven before anything reads them, and the OU tree retired once nothing depends on it

A sample PMP-style project plan for the cross-track foundation of the Attribute-Driven Migration companion guide and its two technical deep-dive decks: reading the OU tree, the attribute schema and AD-to-Entra mapping, the coded extension-attribute slots, proving the attributes, sync, the dynamic group library with its guards, administrative units, Conditional Access personas, device and server targeting conventions, PIV and CAC binding, the mover proof, cut-over and the OU tree’s retirement, and drift. Handoffs to the track plans and the program’s gates are linked milestones with computed margins; every decision has an owner and a decide-by week.
NoteA sample plan, not a commitment

This is an illustrative plan built from the workbook’s books, in the form a project manager would baseline: a work breakdown, a schedule network, a computed critical path, decision points, gates and risks. The durations are illustrative, sized to the books’ roadmap weeks. Replace them with the agency’s own estimates, then baseline the result. The plan names roles, not people, and no specific agency.

Plan at a glance

Plan at a glance
Plan type Project: The nine stages of the companion guide, PIV binding and the mover proof: the parts the four tracks share, with the tracks themselves handed to their own plans
Built from Books 01, 02, 03, 04, 05 and 07; the companion guide
Sponsor Executive sponsor and CIO; CISO
Plan manager Identity engineering lead, with the data architect, the HR integrated project team lead and the endpoint lead
Duration 40 weeks (200 working days), computed from the network
Work 30 tasks, 10 gates, 8 decision points, 28 milestones from other plans
Critical path 5 of 76 items; 11 more within 5 days of it
Calendar Week 1 = the program’s Phase 0 approval; five working days a week

This plan runs the shared foundation of the Attribute-Driven Migration companion guide: the part of the move from Active Directory to Entra ID that no single track owns. In AD, an object’s place in the OU tree decided what applied to it. In Entra ID, what the object says about itself decides. So the attributes have to be defined once, written by exactly one source, proved true, and only then read by groups, administrative units, Conditional Access, Intune and Azure Policy. The plan follows the guide’s nine stages in the order the two technical deep-dive decks present them: Part 1, the model and the HR track (▶ watch), and Part 2, devices, servers, non-person identities and running the migration (▶ watch). The step-by-step work, with the validation kit check that proves each gate, is in Attribute-Driven Migration: An Implementation Guide, and the three-part Deeper Dive Implementation series walks those gates at working level (Part 1, Part 2, Part 3).

It doesn’t re-plan the four tracks. The HR track is the Identity Lifecycle & Provisioning plan, built through the implementation guide Building Book 03’s HR Pipeline. The Intune and Arc tracks are the Endpoint & Device plan, with servers under Arc as its Phase 4. The non-person track is the Non-Person Identity Modernization plan. This plan takes from them the decisions it builds on (the HR plan’s person key, authority map and mover automation) and hands them the conventions they build on (the slot register, device and server targeting, the key that records owners and sponsors). It runs inside the program master schedule. Most of its work lands just before the program task that uses it: the attribute taxonomy (P1.1), the group and unit design (P1.2), the Conditional Access design (P1.5), the sync design (P1.7), the pilot assignments (P2.2) and PIV sign-in (P2.8). Its last phases follow the program’s rollout to G3 and retire the OU tree before the program freezes AD (P5.1).

Schedule

Gantt chart of the Attribute-Driven Migration plan over 40 weeks, grouped by phase. Critical-path tasks are red bars, other tasks are blue bars with a grey line showing their float, gates are violet diamonds, decisions are amber diamonds and milestones from other plans are green diamonds. The tables below give every date and float.

The schedule as a Gantt chart: 40 weeks, with the critical path in red.

Critical path

The computed critical path doesn’t start in week 1. This plan’s early work lands ahead of the program and track tasks that use it, so it carries float, and its finish is set by the program’s rollout. The zero-float chain starts at the program’s G3 (end of week 36). First the transitional sync rules that still read OU placement come out (AT8.3). Once the program has retired the OU-based groups (P4.2, week 38), the OU tree is frozen (AT8.4). The last full drift cycle then closes Gates 8 and 9 in week 40. The only way to finish sooner is a shorter rollout.

Before G3, the plan works against deadlines in the program and the track plans, and the margins are what to watch. The tightest are two working days each: the pilot’s shadow comparison (AT4.4) before the program assigns the pilot’s policies (P2.2), and the non-person conventions (AT5.4) before the Non-Person Identity plan starts recording sponsors (NP1.2). Next, with four days each, come the device targeting conventions (AT5.2) before the Endpoint plan builds its policy library (E1.2), and Gate 0 before the program’s G0. The schema waits on the Identity Lifecycle plan’s person key (D-I1) and attribute authority map (I1.2, week 3), and Gate 1 still reaches the program’s attribute taxonomy (P1.1) with eight days in hand. The group library and unit design reach the program’s group design (P1.2) with eight, the persona set reaches the Conditional Access design (P1.5) with twelve, and the PIV binding pilot reaches the program’s PIV sign-in (P2.8) with ten. The mover proof waits on the HR plan’s mover automation (I4.3, week 12) and closes 17 days before the program’s G2. Gate 8 lands 20 working days before the program freezes AD (P5.1), and Gate 9 40 before G5. The writer of the PIV binding after AD (D-AT7) can wait until the end of week 36, because it must be decided before the program starts moving issuance off AD CS (P4.5, which follows G3). Deciding it earlier leaves time for the open pilot to report.

The critical path, in order. Each item has zero total float: a day lost on any of them is a day lost at the finish.

The critical path
# ID Item Owner or approver When
1 AT8.3 Transitional rules removed: the account-type sync rule that reads OU placement, OU-based scoping filters and the provisioning OU computation for cloud-mastered populations Identity engineering wk 37–38
2 AT8.4 OU tree frozen: hand-made delegations removed; no OU drives access, scoping or policy; the tree’s final export archived in Git as the record Identity engineering wk 39–40
3 AT9.3 A full drift cycle on the whole estate: findings closed at the source; the nightly plan zero-action Security operations, with HR wk 39–40
4 ATG8 Gate 8 — OU tree retired as a control CISO end of wk 40
5 ATG9 Gate 9 — Attributes kept true CISO end of wk 40

Near-critical. These items have 5 working days of float or less. Track them weekly: once their float is spent, they join the critical path.

Near-critical items
ID Item Float When
D-AT1 Attribute schema: the store and the single writer for every attribute that drives access, in all four tracks 2 d end of wk 3
AT5.4 Non-person conventions: owners and sponsors recorded by the enterprise person key; custom security attributes for service principals (system, environment, tier) defined 2 d wk 3–4
ATG3 Gate 3 — Attributes flowing 2 d end of wk 8
AT4.4 Shadow comparison on the pilot: each dynamic group against the group it replaces, every add and remove explained; membership-delta alerts on 2 d wk 9–10
AT1.1 AD attribute inventory: which attributes are populated, by whom and how fully; which extension attributes are free to carry codes 3 d wk 1
AT1.2 AD-to-Entra mapping for every attribute that drives access, per object type: users, devices, Arc servers, service principals; the store for each from the store table 3 d wk 2–3
AT0.1 OU tree exported read-only: placement and size, GPO links at domain, OU and site, inheritance, and hand-made delegations; every OU and each GPO half tagged with its track 4 d wk 1–2
AT0.2 A decision for every security group: keep synced, convert to cloud-only, convert to dynamic, or retire 4 d wk 2–4
D-AT2 The coded slot register: which extension attribute carries which code, on users and on devices 4 d end of wk 3
AT5.2 Device targeting conventions: device slots written at registration by the provisioning service; dynamic device groups only where a rule reads tier or role; filters otherwise; no dynamic device group as an exclusion 4 d wk 3–4
ATG0 Gate 0 — The tree read 4 d end of wk 4

Decision points

Each decision is a zero-duration milestone in the network. Decide by is its late finish: the last week it can be made without moving the plan’s finish. A decision with zero float sits on the critical path, so the meeting that makes it should be booked before the plan is baselined. Decision rights follow Book 01, Chapter 09.

Decision points, by decide-by date
ID Decision Decides Needed by Decide by Float Options If it’s late
D-AT1 Attribute schema: the store and the single writer for every attribute that drives access, in all four tracks Data architect D-AT2, AT1.4, AT5.4 end of wk 3 2 d Native properties first, then extension attributes 1–15 for what rules read, directory extensions for more slots, custom security attributes for sensitive values rules don’t need, device properties, Azure tags and certificateUserIds (the store table); or a broader use of directory extensions from the start No slot can be assigned, and every group rule, persona and targeting convention waits
D-AT2 The coded slot register: which extension attribute carries which code, on users and on devices Data architect, with HR for the code lists AT1.3, AT5.1, AT5.2 end of wk 4 4 d The program attribute map (organization, worker type and position category in extensionAttribute10 to 12; region, cost center, division, account type, clearance and DoNotSync in their slots; device tier, role and environment on the device object); or an agency map that keeps the same rule: codes, never names, one writer per slot Rules and filters are written against slots that may move, and every one is rewritten later
D-AT4 Restricted management, unit by unit, before each unit exists Identity engineering AT4.3 end of wk 6 16 d No (the default): the unit scopes writes and stays in governance automation; yes, for a small set of sensitive accounts, accepting that they leave PIM, entitlement management, Lifecycle Workflows and access reviews A unit is created without the decision, and restriction can’t be changed afterward
D-AT5 The persona set the Conditional Access library targets CISO X-P15, ATG5 end of wk 6 12 d The program’s personas, built from the worker type and account type codes; personas plus division-specific overlays; fewer personas with more exclusions (not recommended) The Conditional Access design runs in report-only without the groups it will enforce on
D-AT3 Correlation threshold before any rule grants access Authorizing official, through the agency’s risk governance ATG2 end of wk 9 20 d 99% of the pilot cohort correlated (a proposed starting point); a risk-tiered threshold, stricter for privileged and leaver-sensitive populations; 100% with a dated exception list No group can be piloted, because nobody has said how true the attributes must be
D-AT6 Required affinity binding for PIV and CAC CISO AT6.2 end of wk 11 8 d High affinity in production (the program’s position), with a custom rule per issuer during the pilot; low affinity until coverage is complete, with a dated end; mixed by issuer PIV sign-in goes to the pilot at the tenant default, which is low affinity
D-AT8 Drift severity and response times CISO AT9.1 end of wk 13 40 d Book 03’s classes (missing identity, stale access, orphan account, attribute drift, unauthorized write, credential drift, contractor credential drift, schema drift), which the program’s own drift model, Book 13’s five classes, groups (the mapping is not yet specified here), with high severity closed in days and the rest on a dated plan; a stricter clock for unauthorized writes to the access slots Drift findings pile up with nobody obliged to close them
D-AT7 Who writes the binding after AD ICAM governance body X-P45 end of wk 36 130 d The card management system writes certificateUserIds through Microsoft Graph at issuance (design guidance, an open pilot); Entra Connect keeps syncing from altSecurityIdentities while any AD remains; manual entry by a Privileged Authentication Administrator (not at scale) User issuance can’t move off AD CS, because nothing writes the binding without AD

Gates

A gate opens the work that names it as a predecessor, which is usually the next phase but not always. The approver signs it against the criteria, from evidence in the repository.

Gates
Gate When Approver Criteria
Gate 0 — The tree read end of wk 4 Identity engineering lead Inventory in Git, site-linked GPOs included; every OU and every GPO half tagged with its track; a decision for every group; the OU-to-unit mapping drafted; nothing changed in the forest
Gate 1 — Schema and slots signed end of wk 4 ICAM governance body Every attribute that drives access has one store, one writer and one owner, in all four tracks; the slot register published; the person key carried in employeeId in both directories; codes, never display names, in anything a rule reads
Gate 2 — Attributes proven for the pilot end of wk 5 CISO Correlation threshold met on the pilot cohort; every enabled account correlated or on a dated exception list; no duplicate keys; every other write path to the access slots removed in AD and Entra ID; logs leaving Entra ID
Gate 3 — Attributes flowing end of wk 8 Identity engineering lead Object counts within ±1%; no sync errors; every slot in the register arrives in Entra ID with the value HR sent; shadow-mode differences explained; both match types blocked outside a planned window
Gate 4 — Group library and units designed end of wk 5 Identity engineering lead Every governed group on one of the two patterns, on codes, with guards; every unit rule mirroring its group rule; restriction decided for every unit; every role assignment in the matrix
Gate 5 — Targeting conventions set end of wk 4 CISO Personas from authoritative codes, grant and block in pairs, empty slots reported; device and server conventions published and handed to the Endpoint plan; non-person owners and sponsors keyed to the person key
Gate 6 — PIV binding proven on the pilot end of wk 10 CISO Every pilot card holder bound; high affinity piloted with no lockouts; phishing-resistant strength for CBA users; the leaver removes the binding as well as revoking the card
Gate 7 — Mover proven across the tracks end of wk 13 CISO The test mover’s access changed only through the attributes, within the measured latency; nothing assigned by hand; the device’s groups unchanged; the sponsor of any non-person identity the user sponsors notified; the change traced from the personnel action to the drift report
Gate 8 — OU tree retired as a control end of wk 40 CISO Every population cut over by attribute query with its gate passed; no sync rule, scoping filter, group, delegation or policy reads OU placement; the final tree archived; rollback by re-enabling, never by re-creating
Gate 9 — Attributes kept true end of wk 40 CISO Valid attributes for every HR-listed worker; every group on one of the two patterns; every unit rule mirroring its group with processing on; every policy targeting only governed groups; zero open high-severity drift findings; logs outside Entra ID; the six lifecycle metrics on the ConMon cadence

Work breakdown and schedule

Every row, by phase. Float is total float in working days; bold rows are on the critical path. Each row links to the chapter it comes from.

Phase 0 — Read the tree

Phase 0 — Read the tree
ID Item Type Owner or approver Days Predecessors When Float
AT0.1 OU tree exported read-only: placement and size, GPO links at domain, OU and site, inheritance, and hand-made delegations; every OU and each GPO half tagged with its track Task Identity engineering 8 — wk 1–2 4 d
AT0.2 A decision for every security group: keep synced, convert to cloud-only, convert to dynamic, or retire Task Identity engineering, with application owners 8 AT0.1 wk 2–4 4 d
AT0.3 OU-to-unit mapping drafted: which OU delegations become administrative units, and which become Azure RBAC scopes for servers Task Identity engineering 4 AT0.1 wk 2–3 8 d
AT0.4 GPO settings split by track: user halves to the HR track’s policy design, computer halves to the Endpoint plan Task Identity engineering, with the endpoint lead 4 AT0.1 wk 2–3 8 d
X-EG0 Device and server observation signed off (Endpoint plan, Gate 0) External CISO / ISSO (Endpoint & Device Modernization plan) — AT0.4 end of wk 4 fixed date
X-NPG0 Non-person identities inventoried (Non-Person Identity plan, Gate 0) External ISSO (Non-Person Identity Modernization plan) — AT0.1 end of wk 4 fixed date
ATG0 Gate 0 — The tree read Gate Identity engineering lead — AT0.2, AT0.3, AT0.4 end of wk 4 4 d
X-G0 Program G0 — Ready to Plan: the read-only assessment committed External Steward (backup: executive sponsor; program) — ATG0 end of wk 4 fixed date

Phase 1 — Schema and slots

Phase 1 — Schema and slots
ID Item Type Owner or approver Days Predecessors When Float
AT1.1 AD attribute inventory: which attributes are populated, by whom and how fully; which extension attributes are free to carry codes Task Identity engineering 5 — wk 1 3 d
X-DI1 Enterprise person key, and how source keys map to it (Identity Lifecycle plan, D-I1) External ICAM governance body, with HR and identity engineering (Identity Lifecycle & Provisioning plan) — — end of wk 1 3 d
AT1.2 AD-to-Entra mapping for every attribute that drives access, per object type: users, devices, Arc servers, service principals; the store for each from the store table Task Data architect, with identity engineering 7 AT1.1, X-DI1 wk 2–3 3 d
X-I12 Attribute authority map signed (Identity Lifecycle plan, I1.2) External ICAM governance body (Identity Lifecycle & Provisioning plan) — — end of wk 3 2 d
D-AT1 Attribute schema: the store and the single writer for every attribute that drives access, in all four tracks Decision Data architect — AT1.2, X-I12 end of wk 3 2 d
D-AT2 The coded slot register: which extension attribute carries which code, on users and on devices Decision Data architect, with HR for the code lists — D-AT1 end of wk 3 4 d
AT1.3 Slot register published: one writer per slot, the code list owner, what reads it; the help desk, self-service and Exchange write paths listed for removal Task Data architect 4 D-AT2 wk 3–4 8 d
AT1.4 Device, server and non-person attribute authorities named: the procurement record through the Autopilot group tag, the asset record through Arc onboarding tags, the owning system’s record Task Data architect, with the endpoint lead 3 D-AT1 wk 3–4 6 d
ATG1 Gate 1 — Schema and slots signed Gate ICAM governance body — AT1.3, AT1.4 end of wk 4 8 d
X-P11 Attribute taxonomy finalized (program P1.1) External Platform teams (program) — ATG1 end of wk 5 fixed date

Phase 2 — Prove the attributes

Phase 2 — Prove the attributes
ID Item Type Owner or approver Days Predecessors When Float
X-I15 HR data baselined; employeeId populated; orphan candidates owned (Identity Lifecycle plan, I1.5) External HR (Identity Lifecycle & Provisioning plan) — — end of wk 4 20 d
AT2.1 Coverage baseline across the tracks: uncorrelated accounts, empty coded slots, counts per organization code against an HR export, duplicate keys; device and server attribute coverage Task Identity engineering 5 ATG1, X-I15 wk 4–5 20 d
D-AT3 Correlation threshold before any rule grants access Decision Authorizing official, through the agency’s risk governance — AT2.1 end of wk 5 20 d
AT2.2 Other write paths removed: help desk and self-service edits to the access slots, Exchange custom-attribute cmdlets, write rights on the target OUs Task Identity engineering, with security 8 AT1.3 wk 4–5 17 d
AT2.3 Entra ID sign-in, audit and provisioning logs routed outside Entra ID before the pilot’s first change Task Security operations 5 ATG1 wk 4–5 20 d
ATG2 Gate 2 — Attributes proven for the pilot Gate CISO — D-AT3, AT2.2, AT2.3 end of wk 5 17 d

Phase 3 — Sync

Phase 3 — Sync
ID Item Type Owner or approver Days Predecessors When Float
AT3.1 Sync mapping for the slot register: carriers in the provisioning apps’ target lists, date mappings, the transitional account-type rule, the DoNotSync filter; soft and hard match blocked Task Identity engineering 5 ATG1 wk 4–5 8 d
X-P17 Sync and DNS Private Resolver designs (program P1.7) External Platform teams (program) — AT3.1 end of wk 6 fixed date
X-IG3 HR feed live for the foundation scope, shadow differences explained (Identity Lifecycle plan, Gate 3) External ISSO (Identity Lifecycle & Provisioning plan) — — end of wk 8 2 d
ATG3 Gate 3 — Attributes flowing Gate Identity engineering lead — AT3.1, X-IG3, ATG2 end of wk 8 2 d

Phase 4 — Groups and administrative units

Phase 4 — Groups and administrative units
ID Item Type Owner or approver Days Predecessors When Float
AT4.1 Dynamic user group library: node and functional rules on codes; every access rule guarded by accountEnabled and userType and excluding agents’ accounts; nesting flattened; no memberOf Task Identity engineering, with application owners 5 ATG1, AT0.2 wk 4–5 8 d
AT4.2 Rules checked before they exist in production: guards, codes not names, paused processing; each rule tested against named users Task Identity engineering 3 AT4.1 wk 5 8 d
D-AT4 Restricted management, unit by unit, before each unit exists Decision Identity engineering — AT0.3 end of wk 3 16 d
AT4.3 Unit registry: tenant readers, department and division units whose rules mirror the group rules; scoped roles to PIM-eligible role-assignable groups; each unit created before the groups it holds Task Identity engineering 5 D-AT4, ATG1 wk 4–5 11 d
ATG4 Gate 4 — Group library and units designed Gate Identity engineering lead — AT4.2, AT4.3 end of wk 5 8 d
X-P12 Dynamic group design tested; enterprise groups and administrative units built (program P1.2) External Platform teams (program) — ATG4 end of wk 7 fixed date
X-P21S Pilot attributes, groups and units going live (program P2.1, its start) External Platform teams (program) — — end of wk 8 2 d
AT4.4 Shadow comparison on the pilot: each dynamic group against the group it replaces, every add and remove explained; membership-delta alerts on Task Identity engineering, with application owners 8 X-P21S, ATG3 wk 9–10 2 d
X-P22 Pilot Conditional Access and Intune policies assigned (program P2.2, its start) External Platform teams (program) — AT4.4 end of wk 10 fixed date

Phase 5 — Personas and targeting conventions

Phase 5 — Personas and targeting conventions
ID Item Type Owner or approver Days Predecessors When Float
AT5.1 Conditional Access personas from coded attributes (worker type for internals and externals); every grant paired with a block; empty-slot users reported; emergency access excluded Task Identity engineering 5 D-AT2 wk 3–4 12 d
D-AT5 The persona set the Conditional Access library targets Decision CISO — AT5.1 end of wk 4 12 d
X-P15 Conditional Access design running in report-only (program P1.5) External CISO (program) — D-AT5 end of wk 6 fixed date
AT5.2 Device targeting conventions: device slots written at registration by the provisioning service; dynamic device groups only where a rule reads tier or role; filters otherwise; no dynamic device group as an exclusion Task Endpoint lead, with the data architect 3 D-AT2 wk 3–4 4 d
X-E12 Intune policy library built unassigned, with groups, filters and scope tags (Endpoint plan, E1.2, its start) External Endpoint engineering (Endpoint & Device Modernization plan) — AT5.2 end of wk 4 fixed date
AT5.3 Server targeting conventions: the Arc tag taxonomy drawn from the asset record and aligned with the device slots; resource groups as the delegation scope Task Server infrastructure, with the data architect 3 AT1.4 wk 4 6 d
X-E42 Tag taxonomy fixed from the asset record (Endpoint plan, E4.2) External Server infrastructure (Endpoint & Device Modernization plan) — AT5.3 end of wk 5 fixed date
AT5.4 Non-person conventions: owners and sponsors recorded by the enterprise person key; custom security attributes for service principals (system, environment, tier) defined Task Identity engineering, with the identity governance officer 3 D-AT1 wk 3–4 2 d
X-NP12 AI accountability: sponsors mastered in HR (Non-Person Identity plan, NP1.2, its start) External Sponsoring offices, with the identity governance officer (Non-Person Identity Modernization plan) — AT5.4 end of wk 4 fixed date
ATG5 Gate 5 — Targeting conventions set Gate CISO — D-AT5, AT5.2, AT5.3, AT5.4 end of wk 4 53 d

Phase 6 — PIV and CAC binding

Phase 6 — PIV and CAC binding
ID Item Type Owner or approver Days Predecessors When Float
AT6.1 Binding coverage measured: certificateUserIds or altSecurityIdentities present and correct for every pilot card holder; the card management system named as the binding writer Task Identity engineering, with the PIV program office 5 ATG3 wk 9 8 d
D-AT6 Required affinity binding for PIV and CAC Decision CISO — AT6.1 end of wk 9 8 d
AT6.2 High affinity piloted on the pilot cohort before the tenant setting changes; multifactor binding rule by issuer or policy OID Task Identity engineering 5 D-AT6 wk 10 8 d
X-P28 Certificate-based authentication for PIV and CAC holders (program P2.8) External Platform teams (program) — AT6.2 end of wk 12 fixed date
D-AT7 Who writes the binding after AD Decision ICAM governance body — AT6.2 end of wk 10 130 d
X-P45 User and device issuance off AD CS; smart-card logon GPO retired (program P4.5, its start) External Platform teams (program) — D-AT7 end of wk 36 fixed date
ATG6 Gate 6 — PIV binding proven on the pilot Gate CISO — AT6.2 end of wk 10 27 d

Phase 7 — The mover proof

Phase 7 — The mover proof
ID Item Type Owner or approver Days Predecessors When Float
X-I43 Joiner and mover automation (Identity Lifecycle plan, I4.3) External Identity engineering (Identity Lifecycle & Provisioning plan) — — end of wk 12 12 d
AT7.1 Mover proof on the pilot: one personnel action moves a test user’s organization code; groups, unit, persona and access packages change with no ticket; the device stays put; a drift scan comes back clean Task Identity engineering, with HR 5 X-I43, X-P22, ATG5 wk 13 12 d
ATG7 Gate 7 — Mover proven across the tracks Gate CISO — AT7.1, ATG6 end of wk 13 12 d
X-G2 Program G2 — Pilot Clean External Steward and executive sponsor (co-signed; program) — ATG7 end of wk 16 fixed date

Phase 8 — Cut-over and the OU tree

Phase 8 — Cut-over and the OU tree
ID Item Type Owner or approver Days Predecessors When Float
AT8.1 Wave scopes written as attribute queries whose groups already exist; leaver automation first in every wave Task Identity engineering 3 ATG7 wk 14 12 d
X-D07 Wave plan: which divisions, in which order (program D07) External Executive sponsor and steering committee (program) — AT8.1 end of wk 16 fixed date
AT8.2 Per-wave attribute gate: coverage of the wave’s query, shadow diff, a dry run with writes off, then seven days in which every change traces to HR before the ticket path closes Task Identity engineering 5 AT8.1 wk 14–15 29 d
X-P31 Wave 1, first region (program P3.1) External Platform teams (program) — AT8.2 end of wk 21 fixed date
X-IG5 Populations cloud-mastered (Identity Lifecycle plan, Gate 5) External ISSO (Identity Lifecycle & Provisioning plan) — — end of wk 26 fixed date
X-G3 Program G3 — Rollout Complete External Executive sponsor and steering committee (program) — — end of wk 36 0
AT8.3 Transitional rules removed: the account-type sync rule that reads OU placement, OU-based scoping filters and the provisioning OU computation for cloud-mastered populations Task Identity engineering 10 X-G3 wk 37–38 0
X-P42 OU-based security groups retired (program P4.2) External Platform teams (program) — — end of wk 38 0
AT8.4 OU tree frozen: hand-made delegations removed; no OU drives access, scoping or policy; the tree’s final export archived in Git as the record Task Identity engineering 10 AT8.3, X-P42 wk 39–40 0
ATG8 Gate 8 — OU tree retired as a control Gate CISO — AT8.4 end of wk 40 0
X-P51 AD changes frozen; final assessment (program P5.1, its start) External Program office (program) — ATG8 end of wk 44 fixed date

Phase 9 — Drift, limits and steady state

Phase 9 — Drift, limits and steady state
ID Item Type Owner or approver Days Predecessors When Float
D-AT8 Drift severity and response times Decision CISO — ATG2 end of wk 5 40 d
AT9.1 Drift scans scheduled: HR against the directory, the unit and role registry against the tenant, membership deltas; each track’s own reconciliation pointed at the same findings queue Task Security operations 5 ATG4, ATG3, D-AT8 wk 9 25 d
X-P211 Drift-clean hold on the pilot (program P2.11, its start) External Program office (program) — AT9.1 end of wk 14 fixed date
AT9.2 Limits register: dynamic group and rule limits, the 100-workflow Lifecycle Workflows budget, administrative unit limits, dynamic units’ cloud availability; reviewed with every design change Task Identity engineering 3 ATG4 wk 6 172 d
AT9.3 A full drift cycle on the whole estate: findings closed at the source; the nightly plan zero-action Task Security operations, with HR 10 AT9.1, AT8.3 wk 39–40 0
ATG9 Gate 9 — Attributes kept true Gate CISO — AT9.2, AT9.3, ATG8 end of wk 40 0
X-G5 Program G5 — AD Retired External Executive sponsor and CIO (program) — ATG9 end of wk 48 fixed date

Responsibility

Who owns what in this plan. Each row has one owner; consulted and informed parties follow the decision matrix.

Ownership
Owner or approver Tasks Decisions Gates
Identity engineering 14 1 —
CISO — 3 6
Platform teams (program) 9 — —
Identity engineering lead — — 3
Identity engineering, with application owners 3 — —
Data architect 1 1 —
Executive sponsor and steering committee (program) 2 — —
ICAM governance body — 1 1
ISSO (Identity Lifecycle & Provisioning plan) 2 — —
Program office (program) 2 — —
Security operations 2 — —
Authorizing official, through the agency’s risk governance — 1 —
CISO (program) 1 — —
CISO / ISSO (Endpoint & Device Modernization plan) 1 — —
Data architect, with HR for the code lists — 1 —
Data architect, with identity engineering 1 — —
Data architect, with the endpoint lead 1 — —
Endpoint engineering (Endpoint & Device Modernization plan) 1 — —
Endpoint lead, with the data architect 1 — —
Executive sponsor and CIO (program) 1 — —
HR (Identity Lifecycle & Provisioning plan) 1 — —
ICAM governance body (Identity Lifecycle & Provisioning plan) 1 — —
ICAM governance body, with HR and identity engineering (Identity Lifecycle & Provisioning plan) 1 — —
ISSO (Non-Person Identity Modernization plan) 1 — —
Identity engineering (Identity Lifecycle & Provisioning plan) 1 — —
Identity engineering, with HR 1 — —
Identity engineering, with security 1 — —
Identity engineering, with the PIV program office 1 — —
Identity engineering, with the endpoint lead 1 — —
Identity engineering, with the identity governance officer 1 — —
Security operations, with HR 1 — —
Server infrastructure (Endpoint & Device Modernization plan) 1 — —
Server infrastructure, with the data architect 1 — —
Sponsoring offices, with the identity governance officer (Non-Person Identity Modernization plan) 1 — —
Steward (backup: executive sponsor; program) 1 — —
Steward and executive sponsor (co-signed; program) 1 — —

Assumptions

  • The person key is decided in the Identity Lifecycle plan (D-I1). This plan carries it in employeeId in both directories. Where the agency already has a long-standing enterprise identifier, such as a Mainframe PIN, that is the natural candidate (Book 03, Chapter 04).
  • Attribute slots follow the program attribute map: organization, worker type and position category in extensionAttribute10 to 12. Codes such as FIN-LED stand in for the agency’s own code lists.
  • Users stay AD-mastered and synced through most of this plan, so their attribute values are written in AD and read-only in Entra ID until each population becomes cloud-mastered (companion guide, Stage 1).
  • The validation kit’s checks are read-only and fixture-tested, not proven against a live tenant. Sync (VK-SYNC-01), the Conditional Access personas (VK-CA-01) and the PIV binding (VK-PIV-01) have checks that cover part of their gates; the rest of each gate’s evidence is the export or report named in the implementation guide.
  • Durations are illustrative. Most of this plan is design and verification work that lands just before a program task uses it; its finish follows the program’s rollout.

Schedule risks

Schedule risks
Risk Effect on the schedule Response
A rule reads an attribute that more than one system writes Access changes with whichever writer ran last, and drift can’t be fixed at the source One writer per attribute in the slot register; other write paths removed before the first rule grants access (AT1.3, AT2.2; Book 03, Chapter 06)
A dynamic rule is written on a display name, or without guards The group breaks when someone retypes a name, or includes disabled accounts and guests Rules on codes only, every rule with accountEnabled and userType guards, checked by the validation kit before any rule grants access (AT4.2; companion guide)
A soft or hard match overwrites cloud values with stale AD values Coded attributes revert across a population at the next sync Clean AD first, keep both match types blocked outside a planned window (AT3.1; Book 02, Chapter 09)
A Conditional Access persona includes a group built from an empty attribute Users whose attribute is empty are silently outside the policy Pair every grant with a block, and report empty slots before enforcement (AT5.1; Book 04, Chapter 03)
The tenant is set to high-affinity PIV binding before every account’s value is right Card holders are locked out Measure binding coverage, then pilot high affinity before the tenant setting changes (AT6.2; companion guide)
Entra ID’s logs expire before an assessor asks for them The evidence for the pilot’s changes is gone, and the logs aren’t retroactive Route logs outside Entra ID from the pilot’s first day (AT2.3; Book 03, Chapter 11)

Baseline and change control

  • Baseline the plan when its first gate is approved: the YAML file, as merged, is the baseline.
  • Report weekly, green, yellow or red, against the baseline (Book 01, Chapter 12). Report float, not percent complete: a task’s float says how much slip the plan can still absorb.
  • Change the plan only through a reviewed pull request that edits the YAML and regenerates this page, so every change to a date or a dependency has an author, a reviewer and a reason.
  • Re-baseline at each gate, after the approver signs it, and whenever a critical-path decision is made late.

Download and adapt

Downloads
File Use it for
attribute-driven-migration.xml Microsoft Project desktop (open the XML file; it keeps the dependencies, milestones and owners). The dates start on a placeholder Monday: change the project start date.
attribute-driven-migration.csv Excel or any other scheduling tool: every row with its dependencies, early and late dates and float
attribute-driven-migration-azure-boards.csv Azure DevOps Boards: an Epic per phase and a Feature per task, gate and decision, with dates and tags (see below)
attribute-driven-migration-dependencies.csv · add-azure-boards-links.ps1 The plan’s predecessor links, and a script that adds them in Azure Boards after the import
attribute-driven-migration-jira.csv Jira: an Epic per phase and a Task per task, gate and decision, with dates, labels and Blocks links (see below)
attribute-driven-migration.yaml The source. Edit the durations, owners and dependencies, then run python scripts/project_plans/build.py to recompute the critical path and regenerate this page, the chart and the downloads.
TipImporting this plan into Azure DevOps Boards
  1. In the project, select Boards > Queries > Import work items, choose attribute-driven-migration-azure-boards.csv, check the results and select Save items. It creates one Epic per phase with a Feature under it for each task, gate and decision, with start and target dates, which is what Delivery Plans show. Epic and Feature exist in the Agile, Scrum and CMMI processes; in the Basic process, change Feature to Issue in the file first.
  2. The import can’t create dependency links or assign people. To add the predecessor links, sign in with az login, add the CLI extension with az extension add --name azure-devops, and run ./add-azure-boards-links.ps1 -Organization https://dev.azure.com/<org> -Project <project> -Plan attribute-driven-migration beside attribute-driven-migration-dependencies.csv. It finds the imported items by their fmw-id- tags and links each one to its predecessors.
  3. Assign people in Boards: each item carries its owner role as an Owner - … tag, and critical-path items carry Critical path. Azure Boards links don’t hold lag or start-to-start timing; each item’s description keeps them.

The dates count from the plan’s placeholder start; shift them when you set the real start. The script hasn’t been run against a live organization yet: test it on a scratch project first.

TipImporting this plan into Jira
  1. Run the CSV importer (in Jira Cloud, Settings > System > External system import > CSV) with attribute-driven-migration-jira.csv. On the second step, set Date format in import file to yyyy-MM-dd.
  2. Map the columns: Work item ID to Work item ID, Work type to Work type, Parent to Parent, Summary, Description and every Labels column to their fields, Start date to the Start date field, Due date to Due date, and every Blocks column to the Blocks link type. Each phase becomes an Epic with a Task under it for each task, gate and decision; each Blocks column makes that row’s item block the item it names, which carries the plan’s dependencies.
  3. Assign people in Jira: each item carries its owner role as an owner-… label, and critical-path items carry critical-path. Jira links don’t hold lag or start-to-start timing; each description keeps them.

Test the import on a scratch project with a few rows first: the importer doesn’t remove duplicate links and Jira has no bulk delete for them. If the Blocks links don’t come through on your site, import the items first and add the links from the plan’s dependency list in a second pass, as Atlassian recommends. The dates count from the plan’s placeholder start.

TipOpening this plan in Project or Planner
  • Microsoft Project desktop opens the XML file directly, with every dependency, milestone and owner.
  • Microsoft Planner has no file import of its own: it doesn’t read XML, CSV or Excel. To bring this plan into a Planner premium plan, open the XML file in Project desktop, save it as an .mpp file, and import that through the Project Power App. Tasks, durations, dependencies and milestones come across; resources and baselines don’t, so assign owners again in Planner.
  • Without Project desktop, the CSV can feed a Power Automate flow that creates the tasks one by one, but dependencies in a premium plan need Microsoft’s Project schedule APIs, so that’s a build, not an import.
  • In a government cloud tenant, check that premium plans are available before relying on Planner for this schedule: Microsoft notes that converting a basic plan to a premium plan isn’t available in GCC.

Project for the web was retired on August 1, 2025, and Project Online on September 30, 2026; Planner is their successor. Project desktop is unaffected.