Project plan · Sample · Project

Network & Access Modernization: Naming Plane, Governed Transport and Edge Enforcement

A sample project plan for Books 08 and 09: the naming and addressing plane, a governed-transport pilot behind a secured governor, network access control, and the gated retirement of AD DNS and DHCP

A sample PMP-style project plan for the Network & Access Modernization project, built from Books 08 and 09: a work breakdown by project phase, a computed critical path tied to the program’s own DNS tasks, every gate with its approver and criteria, and the intermediate decisions (DDI platform, resolver path, egress pattern, boundary change, fabric go-live, NAC platform) with owners and decide-by weeks.
NoteA sample plan, not a commitment

This is an illustrative plan built from the workbook’s books, in the form a project manager would baseline: a work breakdown, a schedule network, a computed critical path, decision points, gates and risks. The durations are illustrative, sized to the books’ roadmap weeks. Replace them with the agency’s own estimates, then baseline the result. The plan names roles, not people, and no specific agency.

Plan at a glance

Plan at a glance
Plan type Project: Project Phases 0 to 5, from naming-plane ownership to the decommission of AD DNS and DHCP
Built from Books 08 and 09
Sponsor Executive sponsor and CIO
Plan manager Network and access project lead, with the DNS/DDI team lead and the network engineering lead
Duration 46 weeks (227 working days), computed from the network
Work 22 tasks, 6 gates, 12 decision points, 5 milestones from other plans
Critical path 4 of 45 items; 1 more within 5 days of it
Calendar Week 1 = the program’s Phase 0 approval; five working days a week

This plan builds the Network & Access Modernization project from Book 08 (DNS, DHCP and IPAM) and Book 09 (transport, TIC 3.0 and network access control). It adapts the charter’s phases in Book 09, Chapter 09, moving identity availability into Phase 3 and adding Phases 2 and 5: naming and addressing first, then a governed-transport pilot behind a secured governor, then enforcement at the customer edge, and last Book 08’s gated decommission of AD DNS and DHCP. It runs inside the program master schedule: it takes the cloud resolver from the program’s P1.7, follows the pilot division’s DNS move (P2.6) and the program’s move of the AD-integrated zones (P4.3), and uses the device certificates from P2.7. Its success measures are the charter’s, at pilot scale.

Schedule

Gantt chart of the Network & Access Modernization plan over 46 weeks, grouped by phase. Critical-path tasks are red bars, other tasks are blue bars with a grey line showing their float, gates are violet diamonds, decisions are amber diamonds and milestones from other plans are green diamonds. The tables below give every date and float.

The schedule as a Gantt chart: 46 weeks, with the critical path in red.

Critical path

The computed path is short, and it sits at the end. It starts with the program’s move of the AD-integrated zones (P4.3, week 39), then runs through the 30-day SRV hold, the decommission decision and the ordered retirement of the legacy DNS servers to Gate 5 in week 46, two weeks before the program’s G5. Book 08 makes that tail a set of gates, not dates, so it can’t be compressed: the 30 clean days count only from the last zone move. Most earlier work carries float against this plan’s finish, but one program date binds it much sooner. Coexistence (N1.1) must be in place when the program starts moving the pilot division’s DNS (the start of P2.6, end of week 8), and it finishes with two days to spare, so the cloud resolver from P1.7 and coexistence are tracked as near-critical, and the DDI platform decision (D-N1) has about three weeks of float. The pilot’s own chain runs through the naming plane: the fabric goes live only after Gate 1, which follows the pilot-division move, so a slip in P2.6 moves the pilot cutover and Gate 3 week for week. The NAC chain carries about nine weeks of float once the program’s device certificates (P2.7) arrive.

The critical path, in order. Each item has zero total float: a day lost on any of them is a day lost at the finish.

The critical path
# ID Item Owner or approver When
1 N5.1 SRV hold: every critical locator record resolves from every VNet and site, every 15 minutes, for 30 clean days DNS/DDI team wk 40–44
2 D-N12 Decommission AD DNS and Windows DHCP Executive sponsor and CIO end of wk 44
3 N5.4 Legacy DNS servers and Windows DHCP servers retired in order, DHCP de-authorized last; exports archived; records officer confirms disposition; 7-day burn-in AD administrators wk 44–46
4 NG5 Gate 5 — Legacy name services retired, evidence complete DNS/DDI team end of wk 46

Near-critical. These items have 5 working days of float or less. Track them weekly: once their float is spent, they join the critical path.

Near-critical items
ID Item Float When
N1.1 Coexistence: DDI resolvers deployed, Microsoft DNS and DHCP synchronized read-only, forwarding both ways with one path per namespace 2 d wk 7–8

Decision points

Each decision is a zero-duration milestone in the network. Decide by is its late finish: the last week it can be made without moving the plan’s finish. A decision with zero float sits on the critical path, so the meeting that makes it should be booked before the plan is baselined. Decision rights follow Book 01, Chapter 09.

Decision points, by decide-by date
ID Decision Decides Needed by Decide by Float Options If it’s late
D-N1 DDI platform model Executive sponsor and CIO NG0 end of wk 7 15 d SaaS policy plane; agency-operated DDI inside the boundary; cloud-native services managed as code (enough on its own for a single-cloud agency with no divisional delegation) Coexistence can’t be deployed, and the pilot division’s DNS move (program P2.6) has nothing to move onto
D-N3 Order of zones to move, and the cutover pattern for each DNS/DDI team N1.3 end of wk 21 66 d Per zone: split horizon, subdomain delegation, or progressive migration with conditional forwarding. AD locator records stay where domain controllers can register them, and move last Authority can’t move zone by zone; the pilot division’s zones wait
D-N10 RADIUS and NAC platform, and the trigger that retires NPS (D3) Executive sponsor and CIO N4.1 end of wk 24 112 d NPS through the hybrid-joined phase only; an on-premises NAC platform reading Intune compliance; a cloud-delivered NAC or RADIUS service with the right FedRAMP authorization; VPN or ZTNA federated to Entra ID for remote access Enforcement can’t be designed, and Entra-joined devices can’t be admitted before cloud-native cutover removes the AD objects NPS relies on
D-N11 Move the pilot sites from monitor mode to wired enforcement Network engineering N4.2 end of wk 30 47 d Enforce on workstation ports; stay in monitor mode until the baseline’s exceptions are closed Wired and wireless enforcement wait, and devices are still admitted before they authenticate
D-N4 Control-plane hosting model, recorded as the boundary disposition Executive sponsor and CIO N2.1 end of wk 31 138 d An on-premises control plane; Cisco Catalyst SD-WAN for Government, cloud-hosted and FedRAMP Certified at Class C (Moderate). A hosted controller doesn’t remove the directive’s obligations The control plane can’t be built or hardened, and the pilot waits
D-N5 Egress pattern for each pilot site Network engineering N3.3, D-N7 end of wk 36 143 d A, hairpin; C, governed local breakout (the program’s reference pattern); D, agent-delivered SASE. Never B, bare local breakout Pilot sites can’t be built, and the boundary change can’t name its enforcement points
D-N6 Path to a domain controller for each branch class Network engineering N3.3 end of wk 36 175 d A private path (MPLS, IPsec or the SD-WAN overlay); a ZTNA connector that publishes the domain controllers (single sign-on only); a Kerberos KDC proxy Pilot branches on local breakout lose sign-in, Group Policy and password change while cloud applications keep working
D-N2 Resolver path: the redirect-dns target and the forwarding chain order (Decisions 1 and 2) DNS/DDI team N1.2 end of wk 39 178 d A DDI resolver at the branch; a forwarding proxy in a regional hub. Never a client loopback stub, and any SASE resolver is a forwarding target of the agency resolver, never the redirect target Branch edges can’t be retargeted; Protective DNS, logging and response policy stay off the branch path
D-N7 Boundary change for local egress, decided before the first production cutover Authorizing official D-N9 end of wk 41 135 d Approve the significant change through reauthorization or ongoing authorization; refuse, and the sites stay on their current path No production cutover can start: the boundary change comes first
D-N8 Microsoft 365 Optimize exemption (the SC-7(4) traffic-flow exception) Authorizing official N3.4 end of wk 41 158 d Grant it for a stated duration and review cadence, on named and compensating controls; refuse it Optimize traffic stays on the inspected path at the pilot sites, and the cutover waits
D-N9 Fabric go-live, site by site: governor live, inspecting and logging System owner N3.4 end of wk 41 120 d Turn on the site’s new egress; hold the site on its current path Pilot traffic stays on the old path, and the 30-day stability clock doesn’t start
D-N12 Decommission AD DNS and Windows DHCP Executive sponsor and CIO N5.4 end of wk 44 0 (critical) Decommission once all five gates pass, including 90 days of parallel operation; hold the legacy servers. Never on a date alone Legacy DNS servers and their DnsAdmins exposure stay in service into the program’s AD retirement phase

Gates

A gate opens the work that names it as a predecessor, which is usually the next phase but not always. The approver signs it against the criteria, from evidence in the repository.

Gates
Gate When Approver Criteria
Gate 0 — Inventory committed and decisions owned end of wk 4 DNS/DDI team AD DNS inventory dated, committed and reviewed (Decision 4); every branch’s redirect-dns target read from the running configuration; platform model decided; one named decider for every row of the DNS and network matrices
Gate 1 — Naming plane authoritative for the pilot scope end of wk 17 DNS/DDI team Every name class in the validation matrix resolves correctly from on-premises, each cloud and the branch path; no private endpoint name returns a public address; OCSP and CRL endpoints resolve from every origin; every branch’s redirect-dns target is an agency resolver; resolution-path consistency baselined
Gate 2 — Governor secured before it carries traffic end of wk 9 CISO and ISSO Controller and edges under vulnerability management on BOD 26-04 windows, privileged-access control and off-box logging; every edge in the fleet inventory with its software version and support date; an ED 26-03-style inventory, log collection and patch sequence executable within a day; SD-WAN syslog reaching CISA through CLAW
Gate 3 — Pilot governed and evidenced end of wk 22 CISO Pilot sites stable for 30 days with the control layer live, inspecting and logging to the SIEM; boundary change decided before cutover; SC-7(4) memo signed and site register current; CISA telemetry parity confirmed per site before any legacy circuit ends; one path decision emitted as a claim; the VPN path documented as residual
Gate 4 — Customer edge enforced for the pilot end of wk 36 CISO and ISSO Monitor-mode baseline report filed; wired and wireless enforcement live at the pilot sites; the three minimum detections alerting the SOC; RADIUS accounting, Intune compliance reports and DHCP audit logs kept for assessors; every MAB exception dated
Gate 5 — Legacy name services retired, evidence complete end of wk 46 DNS/DDI team Gates 3 and 4 passed; Chapter 11’s evidence checklist complete, the five decisions checked first; no client impact through the burn-in; logs searchable for six months and retrievable for a year; DnsAdmins and delegated roles reviewed; only the domain’s own zones left on AD DNS, reached by forwarding, until the last domain controllers go

Work breakdown and schedule

Every row, by phase. Float is total float in working days; bold rows are on the critical path. Each row links to the chapter it comes from.

Phase 0 — Charter, alignment and inventory

Phase 0 — Charter, alignment and inventory
ID Item Type Owner or approver Days Predecessors When Float
N0.1 Naming-plane owner confirmed; pilot population defined; remote-access paths and residual VPN use inventoried Task Executive sponsor and CIO 5 — wk 1 15 d
N0.2 AD DNS and DHCP inventory, read-only, committed as JSON; DnsAdmins emptied of non-domain-administrators Task AD administrators 10 — wk 1–2 22 d
N0.3 DDI candidates scored on evidence: Marketplace status, policy-plane coverage, the five decisions, vendor questions in writing Task DNS/DDI team 12 N0.1 wk 2–4 15 d
D-N1 DDI platform model Decision Executive sponsor and CIO — N0.3 end of wk 4 15 d
NG0 Gate 0 — Inventory committed and decisions owned Gate DNS/DDI team — N0.2, D-N1 end of wk 4 15 d

Phase 1 — Naming and addressing

Phase 1 — Naming and addressing
ID Item Type Owner or approver Days Predecessors When Float
X-P17 Cloud DNS Private Resolver deployed (program P1.7) External Platform teams (program) — — end of wk 6 2 d
N1.1 Coexistence: DDI resolvers deployed, Microsoft DNS and DHCP synchronized read-only, forwarding both ways with one path per namespace Task DNS/DDI team 8 NG0, X-P17 wk 7–8 2 d
X-P26S Program starts the pilot division’s DNS move (start of P2.6) External Platform teams (program) — N1.1 end of wk 8 fixed date
D-N2 Resolver path: the redirect-dns target and the forwarding chain order (Decisions 1 and 2) Decision DNS/DDI team — NG0 end of wk 4 178 d
N1.2 Edge retargeted: redirect-dns to agency resolvers, SASE DNS as a forwarding target, order verified in the running configuration Task Network engineering 10 D-N2, N1.1 wk 8–10 157 d
D-N3 Order of zones to move, and the cutover pattern for each Decision DNS/DDI team — N1.1 end of wk 8 66 d
X-P26 Pilot division’s DNS migrated and DHCP re-homed (program P2.6) External Platform teams (program) — — end of wk 11 49 d
N1.3 Non-AD zones, forwarders, GlobalNames and reverse zones moved through the cutover loop Task DNS/DDI team 15 D-N3, X-P26 wk 12–14 49 d
N1.4 Clients and DHCP scopes moved in waves with the program’s divisions (option 6, VNet DNS settings) Task DNS/DDI team 90 N1.3 wk 15–32 49 d
N1.5 Cloud federation: IPAM federation, private endpoint zones published once, validation matrix run from every origin Task Cloud platform teams 15 N1.3 wk 15–17 120 d
NG1 Gate 1 — Naming plane authoritative for the pilot scope Gate DNS/DDI team — N1.2, N1.5 end of wk 17 120 d

Phase 2 — Securing the governor

Phase 2 — Securing the governor
ID Item Type Owner or approver Days Predecessors When Float
D-N4 Control-plane hosting model, recorded as the boundary disposition Decision Executive sponsor and CIO — NG0 end of wk 4 138 d
N2.1 Control plane built and taken through the ED 26-03 sequence: inventory, off-box logs, patch, hunt, harden, syslog to CISA through CLAW Task Network engineering 25 D-N4 wk 4–9 138 d
N2.2 Pilot circuits bought on measured physics: per-site latency and loss recorded, diversity, static addressing confirmed with carriers Task Network engineering 20 NG0 wk 4–8 143 d
N2.3 Boundary change and branch use-case package prepared as a significant change, with the evidence the authorization package needs Task System owner 65 N0.1 wk 2–14 135 d
NG2 Gate 2 — Governor secured before it carries traffic Gate CISO and ISSO — N2.1 end of wk 9 138 d

Phase 3 — Identity-driven access pilot

Phase 3 — Identity-driven access pilot
ID Item Type Owner or approver Days Predecessors When Float
N3.1 Identity claims reachable by every access decision point; gaps listed Task Identity engineering 5 NG0 wk 4–5 158 d
N3.2 Application-to-path routing policy (the SC-7(4) traffic-flow policy), site register and architecture review determination Task System owner 10 N2.2 wk 8–10 158 d
D-N5 Egress pattern for each pilot site Decision Network engineering — N2.2 end of wk 8 143 d
D-N6 Path to a domain controller for each branch class Decision Network engineering — N0.1 end of wk 1 175 d
N3.3 Ten pilot sites built: edges, regional breakout, security service edge, deterministic egress, a monitored path to a domain controller Task Network engineering 25 NG2, D-N5, D-N6, N3.1 wk 9–14 138 d
D-N7 Boundary change for local egress, decided before the first production cutover Decision Authorizing official — N2.3, N3.2, D-N5 end of wk 14 135 d
D-N8 Microsoft 365 Optimize exemption (the SC-7(4) traffic-flow exception) Decision Authorizing official — N3.2 end of wk 10 158 d
D-N9 Fabric go-live, site by site: governor live, inspecting and logging Decision System owner — N3.3, D-N7, NG1, NG2 end of wk 17 120 d
N3.4 Pilot cutover; 30 stable days; CISA telemetry parity confirmed per site; one path decision emitted as a claim Task Network engineering 22 D-N9, D-N8 wk 18–22 120 d
NG3 Gate 3 — Pilot governed and evidenced Gate CISO — N3.4 end of wk 22 120 d

Phase 4 — Customer-edge enforcement

Phase 4 — Customer-edge enforcement
ID Item Type Owner or approver Days Predecessors When Float
D-N10 RADIUS and NAC platform, and the trigger that retires NPS (D3) Decision Executive sponsor and CIO — N0.1 end of wk 1 112 d
X-P27 Cloud PKI certificates issued; Wi-Fi and VPN verified (program P2.7) External Platform teams (program) — — end of wk 14 47 d
N4.1 NAC platform registered for Intune compliance retrieval; policy tiers built; monitor mode on pilot ports with a baseline report Task Network engineering 30 D-N10, X-P27 wk 15–20 47 d
D-N11 Move the pilot sites from monitor mode to wired enforcement Decision Network engineering — N4.1 end of wk 20 47 d
N4.2 Wired enforcement: open mode removed, CoA tested, captive portal up, IoT devices registered in IPAM, detections routed to the SOC Task Network engineering 30 D-N11 wk 21–26 47 d
N4.3 Wireless enforcement on WPA3-Enterprise, then IoT segmentation and a rogue-device tabletop Task Network engineering 50 N4.2 wk 27–36 47 d
NG4 Gate 4 — Customer edge enforced for the pilot Gate CISO and ISSO — N4.3 end of wk 36 47 d

Phase 5 — AD DNS and DHCP decommission

Phase 5 — AD DNS and DHCP decommission
ID Item Type Owner or approver Days Predecessors When Float
X-P43 AD-integrated zones moved, except the domain’s own (program P4.3) External Platform teams (program) — — end of wk 39 0
N5.1 SRV hold: every critical locator record resolves from every VNet and site, every 15 minutes, for 30 clean days Task DNS/DDI team 22 X-P43 wk 40–44 0
N5.2 Inventory reconciled both ways; failover tested on the new resolvers and DHCP; query logs show the old servers idle Task DNS/DDI team 8 X-P43, N1.4 wk 40–41 14 d
N5.3 Hardening: Protective DNS forwarding, encrypted DNS, DNSSEC signing and validation where required, monitoring dashboards Task DNS/DDI team 15 N1.4 wk 33–35 52 d
D-N12 Decommission AD DNS and Windows DHCP Decision Executive sponsor and CIO — N5.1, N5.2 end of wk 44 0
N5.4 Legacy DNS servers and Windows DHCP servers retired in order, DHCP de-authorized last; exports archived; records officer confirms disposition; 7-day burn-in Task AD administrators 10 D-N12 wk 44–46 0
NG5 Gate 5 — Legacy name services retired, evidence complete Gate DNS/DDI team — N5.3, N5.4, NG3, NG4 end of wk 46 0

Responsibility

Who owns what in this plan. Each row has one owner; consulted and informed parties follow the decision matrix.

Ownership
Owner or approver Tasks Decisions Gates
DNS/DDI team 7 2 3
Network engineering 8 3 —
Executive sponsor and CIO 1 4 —
Platform teams (program) 5 — —
System owner 2 1 —
AD administrators 2 — —
Authorizing official — 2 —
CISO and ISSO — — 2
CISO — — 1
Cloud platform teams 1 — —
Identity engineering 1 — —

Assumptions

  • The SD-WAN platform is the program’s platform, Cisco Catalyst SD-WAN, bought on an existing contract vehicle. A new acquisition takes several quarters before a device ships (Book 09, Chapter 10) and would move Phase 2 week for week.
  • The pilot is Book 09, Chapter 11’s ten-site pilot. The office waves that follow, keyed to circuit renewal dates over months 18 to 48, are outside this plan.
  • The tenant is GCC-Moderate, so Microsoft 365 informed network routing isn’t available and path selection rests on the SD-WAN’s own measurements (Book 09, Chapter 12).
  • Book 08’s 90 days of parallel operation are counted from coexistence (N1.1). Counted from the last zone move instead (program P4.3), they end near week 52, past the program’s G5.
  • Durations are illustrative. The NAC rollout follows Book 09, Chapter 07’s four phases over roughly 90 to 180 days.

Schedule risks

Schedule risks
Risk Effect on the schedule Response
Accreditation of branch breakout slips No production cutover can start; Gate 3 slips week for week Start the boundary-change package in week 2 (N2.3); fall back to hub-only breakout (Book 09, Chapter 11)
The control plane is hit by another directive-class flaw Gate 2 reopens and the pilot halts until the governor is secured again Keep the ED 26-03 sequence executable within a day and patch inside BOD 26-04 windows (Book 09, Chapters 05 and 08)
Replacement telemetry to CISA lags the cutover No legacy circuit can end; Gate 3 waits on telemetry parity Start CLAW onboarding with the control plane (N2.1); gate each circuit’s termination on confirmed parity (Book 09, Chapter 11)
Locator records are lost to an early decommission Forest-wide authentication and domain-join failures Decommission through gates, never on a date; hold 30 clean SRV days and archive the exports first (Book 08, Chapter 10)
M-26-14, M-26-15 and BOD 26-04 draw on the same staff Every network task stretches; the pilot slips Name the competing mandates in the plan and staff for them (Book 09, Chapter 10)

Baseline and change control

  • Baseline the plan when its first gate is approved: the YAML file, as merged, is the baseline.
  • Report weekly, green, yellow or red, against the baseline (Book 01, Chapter 12). Report float, not percent complete: a task’s float says how much slip the plan can still absorb.
  • Change the plan only through a reviewed pull request that edits the YAML and regenerates this page, so every change to a date or a dependency has an author, a reviewer and a reason.
  • Re-baseline at each gate, after the approver signs it, and whenever a critical-path decision is made late.

Download and adapt

Downloads
File Use it for
network-access.xml Microsoft Project desktop (open the XML file; it keeps the dependencies, milestones and owners). The dates start on a placeholder Monday: change the project start date.
network-access.csv Excel or any other scheduling tool: every row with its dependencies, early and late dates and float
network-access-azure-boards.csv Azure DevOps Boards: an Epic per phase and a Feature per task, gate and decision, with dates and tags (see below)
network-access-dependencies.csv · add-azure-boards-links.ps1 The plan’s predecessor links, and a script that adds them in Azure Boards after the import
network-access-jira.csv Jira: an Epic per phase and a Task per task, gate and decision, with dates, labels and Blocks links (see below)
network-access.yaml The source. Edit the durations, owners and dependencies, then run python scripts/project_plans/build.py to recompute the critical path and regenerate this page, the chart and the downloads.
TipImporting this plan into Azure DevOps Boards
  1. In the project, select Boards > Queries > Import work items, choose network-access-azure-boards.csv, check the results and select Save items. It creates one Epic per phase with a Feature under it for each task, gate and decision, with start and target dates, which is what Delivery Plans show. Epic and Feature exist in the Agile, Scrum and CMMI processes; in the Basic process, change Feature to Issue in the file first.
  2. The import can’t create dependency links or assign people. To add the predecessor links, sign in with az login, add the CLI extension with az extension add --name azure-devops, and run ./add-azure-boards-links.ps1 -Organization https://dev.azure.com/<org> -Project <project> -Plan network-access beside network-access-dependencies.csv. It finds the imported items by their fmw-id- tags and links each one to its predecessors.
  3. Assign people in Boards: each item carries its owner role as an Owner - … tag, and critical-path items carry Critical path. Azure Boards links don’t hold lag or start-to-start timing; each item’s description keeps them.

The dates count from the plan’s placeholder start; shift them when you set the real start. The script hasn’t been run against a live organization yet: test it on a scratch project first.

TipImporting this plan into Jira
  1. Run the CSV importer (in Jira Cloud, Settings > System > External system import > CSV) with network-access-jira.csv. On the second step, set Date format in import file to yyyy-MM-dd.
  2. Map the columns: Work item ID to Work item ID, Work type to Work type, Parent to Parent, Summary, Description and every Labels column to their fields, Start date to the Start date field, Due date to Due date, and every Blocks column to the Blocks link type. Each phase becomes an Epic with a Task under it for each task, gate and decision; each Blocks column makes that row’s item block the item it names, which carries the plan’s dependencies.
  3. Assign people in Jira: each item carries its owner role as an owner-… label, and critical-path items carry critical-path. Jira links don’t hold lag or start-to-start timing; each description keeps them.

Test the import on a scratch project with a few rows first: the importer doesn’t remove duplicate links and Jira has no bulk delete for them. If the Blocks links don’t come through on your site, import the items first and add the links from the plan’s dependency list in a second pass, as Atlassian recommends. The dates count from the plan’s placeholder start.

TipOpening this plan in Project or Planner
  • Microsoft Project desktop opens the XML file directly, with every dependency, milestone and owner.
  • Microsoft Planner has no file import of its own: it doesn’t read XML, CSV or Excel. To bring this plan into a Planner premium plan, open the XML file in Project desktop, save it as an .mpp file, and import that through the Project Power App. Tasks, durations, dependencies and milestones come across; resources and baselines don’t, so assign owners again in Planner.
  • Without Project desktop, the CSV can feed a Power Automate flow that creates the tasks one by one, but dependencies in a premium plan need Microsoft’s Project schedule APIs, so that’s a build, not an import.
  • In a government cloud tenant, check that premium plans are available before relying on Planner for this schedule: Microsoft notes that converting a basic plan to a premium plan isn’t available in GCC.

Project for the web was retired on August 1, 2025, and Project Online on September 30, 2026; Planner is their successor. Project desktop is unaffected.