Project plan · Sample · Project

Continuous Monitoring & Evidence Fabric: Evidence From the Systems

A sample project plan for Book 13’s continuous-monitoring project: from the evidence contract to a drift loop and a package generated from the stream, timed against the program gates that are measured from data

A sample PMP-style project plan for the Continuous Monitoring & Evidence Fabric project, built from Book 13, Chapter 12: a work breakdown by project phase, a computed critical path timed against the program gates measured from data, every gate with its approver and criteria, and the decisions (repository, severity, actuation ceiling, engine, cadence, reciprocity) with owners and decide-by weeks.
NoteA sample plan, not a commitment

This is an illustrative plan built from the workbook’s books, in the form a project manager would baseline: a work breakdown, a schedule network, a computed critical path, decision points, gates and risks. The durations are illustrative, sized to the books’ roadmap weeks. Replace them with the agency’s own estimates, then baseline the result. The plan names roles, not people, and no specific agency.

Plan at a glance

Plan at a glance
Plan type Project: Book 13, Chapter 12 phases 0 to 4, plus the first quarter of the cadence after cutover
Built from Book 13, with Books 14 and 15
Sponsor Executive sponsor and CIO; the senior accountable official for risk management approves the strategy
Plan manager Steward (program office), with domain leads for the evidence contract, aggregation, drift detection and the authorization package
Duration 23 weeks (111 working days), computed from the network
Work 25 tasks, 6 gates, 7 decision points, 7 milestones from other plans
Critical path 7 of 45 items; 20 more within 5 days of it
Calendar Week 1 = the program’s Phase 0 approval; five working days a week

This plan builds the evidence fabric Book 13, Chapter 12 charters: one evidence contract, at least two sources emitting normalized records, one reconciled picture joined on asset identity, a drift loop for one object class, and authorization artifacts generated from the stream. It follows the chapter’s phases gate for gate, and adds the first quarter of the cadence that Book 14, Chapter 11 and Book 15, Chapter 12 run after cutover. Book 00, Chapter 06 places this project fourth, but the program master schedule can’t wait that long: its G1 and G2 criteria are drift-clean, measured from data, so this plan starts in week 1 and is timed against them.

Schedule

Gantt chart of the Continuous Monitoring & Evidence Fabric plan over 23 weeks, grouped by phase. Critical-path tasks are red bars, other tasks are blue bars with a grey line showing their float, gates are violet diamonds, decisions are amber diamonds and milestones from other plans are green diamonds. The tables below give every date and float.

The schedule as a Gantt chart: 23 weeks, with the critical path in red.

Critical path

The computed path doesn’t start in this plan. It starts in the program: the first drift run on the pilot groups and administrative units can’t begin until the program builds them (its P1.2, end of week 7, which is on the program’s own critical path). From there the path runs through that drift run, the drift loop for identity attributes, Gate 4, the first quarter of the cadence and the quarterly review to Gate 5. The build chain from the charter to one reconciled picture (Gates 0 to 3) carries only 2 days of float against it, so a slip of more than 2 days in the contract, the adapters or the join moves Gate 4 and everything after it.

The margin against the program is the number to watch, because the program file can’t show it. The drift run on the groups and administrative units ends in week 8, 4 working days before G1. On the G2 side, the pilot devices move at the end of week 13 (P2.3), and their posture findings land in contract shape 3 days later: 4 days before the program’s 14-day drift-clean hold begins, and 14 days before G2 itself. The hold, not G2, is the real deadline, because G2’s zero-drift criterion is measured across it. If either margin is spent, G1 or G2 is judged on findings people recorded by hand, which Book 13 allows only when they are written in the contract’s shape. Both margins are computed: they’re the deadlines listed under Links to other plans.

The critical path, in order. Each item has zero total float: a day lost on any of them is a day lost at the finish.

The critical path
# ID Item Owner or approver When
1 M4.1 Pilot groups and administrative units checked against the record; findings written in contract shape Drift detection lead wk 7–8
2 M4.2 Drift loop for identity attributes end to end: snapshot, compare, classify, alert, remediate, verify Drift detection lead wk 8–10
3 MG4 Gate 4 — Drift loop running; package from the stream CISO end of wk 10
4 M5.1 Daily triage, weekly evidence and drift review, and the human-only closure review running Program office wk 10–11
5 M5.2 Months 1 to 3: assessment results and the POA&M regenerated, POA&M reviewed, posture report to the AO ISSO wk 10–22
6 M5.6 Quarterly trend and evidence-quality review, covering the pilot’s drift-clean hold ISSM wk 22–23
7 MG5 Gate 5 — First quarter of the cadence closed from the stream Authorizing official end of wk 23

Near-critical. These items have 5 working days of float or less. Track them weekly: once their float is spent, they join the critical path.

Near-critical items
ID Item Float When
M0.1 Sponsor, lead and the four domain leads named 2 d wk 1
M0.2 Record shape, pilot sources and naming-plane join key confirmed 2 d wk 1–2
D-M2 Pilot scope: the two emitting sources and the drift object class 2 d end of wk 2
MG0 Gate 0 — Pilot scope agreed 2 d end of wk 2
M1.1 Normalized record documented: asset identity, time, control, verdict, evidence reference 2 d wk 2–3
M1.3 Remediation contract shape: class, severity, record version, ladder ceiling, named escalation role 2 d wk 3–4
M1.4 Contract committed to the record by reviewed pull request, with a decision record 2 d wk 4
MG1 Gate 1 — Evidence contract published 2 d end of wk 4
M2.3 Both adapters earn active status: recorded fixtures, live non-production tenant, reference deployment in the boundary 2 d wk 4–5
M2.4 Each adapter’s granted permissions compared with its declaration 2 d wk 5–6
MG2 Gate 2 — Two sources emitting 2 d end of wk 6
M3.1 Records joined on the naming-plane identity plus time for the pilot scope 2 d wk 6–7
M3.2 Unjoinable records counted and reported as a coverage gap 2 d wk 7
MG3 Gate 3 — One reconciled picture 2 d end of wk 7
M4.3 Package artifacts generated from the stream for the pilot: SSP, assessment plan, results, POA&M in OSCAL 2 d wk 7–9
M4.4 Coverage classified per control; gap closure register opened; proven and asserted counted 2 d wk 8–9
M3.3 CMDB reconciliation rule applied; unmatched assets worked in the exception queue 3 d wk 6–7
M1.2 Provenance envelope fixed: source classification, transformation chain, lineage hash 4 d wk 3
M2.5 Telemetry-completeness check scheduled for each source 4 d wk 5
M5.3 Pilot devices’ posture findings written in contract shape, before the program’s drift-clean hold 4 d wk 13–14

Decision points

Each decision is a zero-duration milestone in the network. Decide by is its late finish: the last week it can be made without moving the plan’s finish. A decision with zero float sits on the critical path, so the meeting that makes it should be booked before the plan is baselined. Decision rights follow Book 01, Chapter 09.

Decision points, by decide-by date
ID Decision Decides Needed by Decide by Float Options If it’s late
D-M1 Where the record, schemas, rules and their code live Program office (steward) MG0 end of wk 2 7 d One repository and one merge gate for the record, schemas, runtime code and tests; several repositories The contract can’t be committed; a whole class of drift between the record and the code that reads it stays possible
D-M2 Pilot scope: the two emitting sources and the drift object class CISO MG0 end of wk 2 2 d Two of the identity, endpoint, network and data-platform sources; identity attributes or device posture as the object class Emission and the drift loop can’t be scoped; every later phase waits
D-M3 Severity thresholds and halt triggers for the drift classifier Steward, after board review and an outside reviewer M1.3 end of wk 3 7 d The default rule (severity from drift class and whether the claim is in active use; P1 halts and is never remediated automatically); a severity pinned by the owning book’s check The remediation contract has no severity or window, and can’t be published
D-M4 Actuation ceiling for each pilot operation class Authorizing official M4.2 end of wk 8 20 d Every class at L3 gated actuation, the default; a named low-blast-radius class at L4 under written conditions, such as re-applying a dynamic membership rule from the registry The loop’s remediate step can’t be configured; the drift loop waits
D-M5 Engine that realizes the evidence contract and emits the package Program office (steward) M4.3 end of wk 8 18 d A purpose-built governance platform; a commercial governance, risk and compliance product (buy the native applications first, build only the gaps); native OSCAL tooling Package artifacts can’t be generated; Gate 4 waits
D-M6 Minimum monitoring frequencies in the continuous monitoring strategy Senior accountable official for risk management M5.1 end of wk 10 33 d The program’s cadence as the minimums; agency-set minimums, which the program may exceed but not undercut The cadence can’t start; Phase 5 waits
D-M7 How the agency’s decision reuses each external service’s package Authorizing official M5.5 end of wk 21 55 d An ATO for the agency’s own system using a FedRAMP Certified offering; an authorization to use for a shared service another federal entity authorized; a joint authorization under CA-6(2) The reciprocity records can’t be written; Gate 5 waits

Gates

A gate opens the work that names it as a predecessor, which is usually the next phase but not always. The approver signs it against the criteria, from evidence in the repository.

Gates
Gate When Approver Criteria
Gate 0 — Pilot scope agreed end of wk 2 CISO Sponsor, lead and domain leads named; record shape, pilot sources and join key confirmed; pilot scope agreed
Gate 1 — Evidence contract published end of wk 4 CISO The normalized record and its binding to controls are documented; the contract is published and versioned in the authoritative record
Gate 2 — Two sources emitting end of wk 6 CISO Two sources emitting normalized records on their own cadence; each adapter holds no more than its declaration; a silent source raises an alert
Gate 3 — One reconciled picture end of wk 7 CISO One reconciled picture for the pilot scope, joined on asset identity, with unjoinable records counted, not dropped
Gate 4 — Drift loop running; package from the stream end of wk 10 CISO Drift loop running for one class; package artifacts generated for the pilot; coverage report separates proven from asserted claims
Gate 5 — First quarter of the cadence closed from the stream end of wk 23 Authorizing official Three monthly regenerations from current evidence; every failing item open, excepted with an expiry or reverted to open; each provider report has a named reviewer and a record of review; controls tools can’t monitor have a manual assessment at a stated frequency

Work breakdown and schedule

Every row, by phase. Float is total float in working days; bold rows are on the critical path. Each row links to the chapter it comes from.

Phase 0 — Charter and alignment

Phase 0 — Charter and alignment
ID Item Type Owner or approver Days Predecessors When Float
X-P02 Platform host built and repository seeded External Platform teams (program) — — end of wk 2 8 d
X-G0 Program G0: Ready to Plan External Steward (backup: executive sponsor; program) — — end of wk 4 fixed date
M0.1 Sponsor, lead and the four domain leads named Task Executive sponsor and CIO 3 — wk 1 2 d
D-M1 Where the record, schemas, rules and their code live Decision Program office (steward) — M0.1 end of wk 1 7 d
M0.2 Record shape, pilot sources and naming-plane join key confirmed Task Program office 5 M0.1 wk 1–2 2 d
D-M2 Pilot scope: the two emitting sources and the drift object class Decision CISO — M0.2 end of wk 2 2 d
M0.3 Continuous monitoring strategy drafted, with minimum frequencies and manual assessment of what tools can’t see Task CISO 10 M0.1 wk 1–3 33 d
MG0 Gate 0 — Pilot scope agreed Gate CISO — M0.2, D-M1, D-M2 end of wk 2 2 d

Phase 1 — Evidence contract

Phase 1 — Evidence contract
ID Item Type Owner or approver Days Predecessors When Float
M1.1 Normalized record documented: asset identity, time, control, verdict, evidence reference Task Evidence contract lead 5 MG0 wk 2–3 2 d
M1.2 Provenance envelope fixed: source classification, transformation chain, lineage hash Task Evidence contract lead 4 M1.1 (SS) +2 d wk 3 4 d
D-M3 Severity thresholds and halt triggers for the drift classifier Decision Steward, after board review and an outside reviewer — MG0 end of wk 2 7 d
M1.3 Remediation contract shape: class, severity, record version, ladder ceiling, named escalation role Task Drift detection lead 3 M1.1, D-M3 wk 3–4 2 d
M1.4 Contract committed to the record by reviewed pull request, with a decision record Task Steward 2 M1.2, M1.3, X-P02 wk 4 2 d
MG1 Gate 1 — Evidence contract published Gate CISO — M1.4 end of wk 4 2 d

Phase 2 — Emission

Phase 2 — Emission
ID Item Type Owner or approver Days Predecessors When Float
M2.1 Read-only identity adapter declared: class, mission, pinned API version, permissions Task Platform teams 5 MG0 wk 2–3 7 d
M2.2 Read-only device-posture adapter declared Task Platform teams 5 MG0 wk 2–3 7 d
M2.3 Both adapters earn active status: recorded fixtures, live non-production tenant, reference deployment in the boundary Task Platform teams 6 M2.1, M2.2, MG1 wk 4–5 2 d
M2.4 Each adapter’s granted permissions compared with its declaration Task CISO’s staff 2 M2.3 wk 5–6 2 d
M2.5 Telemetry-completeness check scheduled for each source Task Security operations 3 M2.3 (SS) +3 d wk 5 4 d
MG2 Gate 2 — Two sources emitting Gate CISO — M2.4, M2.5 end of wk 6 2 d

Phase 3 — Aggregation

Phase 3 — Aggregation
ID Item Type Owner or approver Days Predecessors When Float
M3.1 Records joined on the naming-plane identity plus time for the pilot scope Task Aggregation lead 5 MG2 wk 6–7 2 d
M3.2 Unjoinable records counted and reported as a coverage gap Task Aggregation lead 3 M3.1 wk 7 2 d
M3.3 CMDB reconciliation rule applied; unmatched assets worked in the exception queue Task CMDB owner 5 M3.1 (SS) +2 d wk 6–7 3 d
MG3 Gate 3 — One reconciled picture Gate CISO — M3.2, M3.3 end of wk 7 2 d

Phase 4 — Detection and assembly

Phase 4 — Detection and assembly
ID Item Type Owner or approver Days Predecessors When Float
X-P12 Enterprise groups and administrative units built External Platform teams (program) — — end of wk 7 0
M4.1 Pilot groups and administrative units checked against the record; findings written in contract shape Task Drift detection lead 3 X-P12, MG2, M1.3 wk 7–8 0
X-G1 Program G1: Foundation Complete (groups and AUs drift-clean) External Steward (program) — M4.1 end of wk 8 fixed date
D-M4 Actuation ceiling for each pilot operation class Decision Authorizing official — M1.3 end of wk 4 20 d
M4.2 Drift loop for identity attributes end to end: snapshot, compare, classify, alert, remediate, verify Task Drift detection lead 10 M4.1, D-M4, MG3 wk 8–10 0
D-M5 Engine that realizes the evidence contract and emits the package Decision Program office (steward) — MG1 end of wk 4 18 d
M4.3 Package artifacts generated from the stream for the pilot: SSP, assessment plan, results, POA&M in OSCAL Task Authorization package lead 10 D-M5, MG3 wk 7–9 2 d
M4.4 Coverage classified per control; gap closure register opened; proven and asserted counted Task Authorization package lead 5 M3.2, M4.3 (SS) +5 d wk 8–9 2 d
MG4 Gate 4 — Drift loop running; package from the stream Gate CISO — M4.2, M4.3, M4.4 end of wk 10 0

Phase 5 — The cadence after cutover

Phase 5 — The cadence after cutover
ID Item Type Owner or approver Days Predecessors When Float
D-M6 Minimum monitoring frequencies in the continuous monitoring strategy Decision Senior accountable official for risk management — M0.3 end of wk 3 33 d
M5.1 Daily triage, weekly evidence and drift review, and the human-only closure review running Task Program office 5 MG4, D-M6 wk 10–11 0
M5.2 Months 1 to 3: assessment results and the POA&M regenerated, POA&M reviewed, posture report to the AO Task ISSO 60 M5.1 (SS) wk 10–22 0
X-P23 Pilot devices moved by pattern External Platform teams (program) — — end of wk 13 4 d
M5.3 Pilot devices’ posture findings written in contract shape, before the program’s drift-clean hold Task Platform teams 3 X-P23, M2.3, M1.3 wk 13–14 4 d
X-HOLD Program drift-clean hold begins (P2.11) External Program office (program) — M5.3 end of wk 14 fixed date
X-G2 Program G2: Pilot Clean (zero drift for the hold period) External Steward and executive sponsor (co-signed; program) — — end of wk 16 26 d
M5.4 Federal senior information security official named to review each provider’s Ongoing Certification Report Task CISO 3 MG4 wk 10 52 d
D-M7 How the agency’s decision reuses each external service’s package Decision Authorizing official — MG4 end of wk 10 55 d
M5.5 Reciprocity record per external service; first Ongoing Certification Report reviewed and recorded Task ISSM 10 D-M7, M5.4 wk 10–12 52 d
M5.6 Quarterly trend and evidence-quality review, covering the pilot’s drift-clean hold Task ISSM 5 M5.2, M5.3, X-G2 wk 22–23 0
MG5 Gate 5 — First quarter of the cadence closed from the stream Gate Authorizing official — M5.5, M5.6 end of wk 23 0

Responsibility

Who owns what in this plan. Each row has one owner; consulted and informed parties follow the decision matrix.

Ownership
Owner or approver Tasks Decisions Gates
CISO 2 1 5
Platform teams 4 — —
Authorizing official — 2 1
Drift detection lead 3 — —
Platform teams (program) 3 — —
Aggregation lead 2 — —
Authorization package lead 2 — —
Evidence contract lead 2 — —
ISSM 2 — —
Program office 2 — —
Program office (steward) — 2 —
CISO’s staff 1 — —
CMDB owner 1 — —
Executive sponsor and CIO 1 — —
ISSO 1 — —
Program office (program) 1 — —
Security operations 1 — —
Senior accountable official for risk management — 1 —
Steward 1 — —
Steward (backup: executive sponsor; program) 1 — —
Steward (program) 1 — —
Steward and executive sponsor (co-signed; program) 1 — —
Steward, after board review and an outside reviewer — 1 —

Assumptions

  • The pilot object class for the drift loop is identity attributes; device posture follows for the program’s G2 (Book 13, Chapter 12 lets the agency pick either).
  • Authorization and identity drift aren’t detected by a runtime engine yet; the domain books’ checks and people find them, and record them in the remediation contract’s shape (Book 13, Chapter 06).
  • An authoritative naming and addressing plane exists, or will, as the join key (Book 13, Chapter 12); unjoinable records are counted, not dropped.
  • Stakeholders accept honest coverage reporting, proven separated from asserted; Book 13 calls this the assumption most often violated.
  • Durations are illustrative. Replacing the agency’s monitoring tools and evidencing every FedRAMP indicator are out of scope for the first phase.

Schedule risks

Schedule risks
Risk Effect on the schedule Response
The program’s P1.2 or P2.3 slips The drift run or the device findings move with it; G1 or G2 is judged on hand-recorded findings Track the 4-day margin weekly; record any hand-found finding in the remediation contract’s shape (Book 13, Chapter 06)
Sources emit proprietary telemetry that can’t be normalized without synthesis Phase 2 can’t close on two sources An adapter per source translates to the contract; derived values are labeled derived (Book 13, Chapter 08)
Drift detection produces more findings than the agency can remediate Window adherence falls; the drift trend the board reviews rises Severity sets the order; routine classes move to the machine tempo; the rest enter the gap register (Book 13, Chapters 10 and 12)
Authorization-package format requirements change Generated artifacts stop validating Artifacts are generated from the stream, so a format change is a generator change, not a rewrite (Book 13, Chapter 12)

Baseline and change control

  • Baseline the plan when its first gate is approved: the YAML file, as merged, is the baseline.
  • Report weekly, green, yellow or red, against the baseline (Book 01, Chapter 12). Report float, not percent complete: a task’s float says how much slip the plan can still absorb.
  • Change the plan only through a reviewed pull request that edits the YAML and regenerates this page, so every change to a date or a dependency has an author, a reviewer and a reason.
  • Re-baseline at each gate, after the approver signs it, and whenever a critical-path decision is made late.

Download and adapt

Downloads
File Use it for
continuous-monitoring.xml Microsoft Project desktop (open the XML file; it keeps the dependencies, milestones and owners). The dates start on a placeholder Monday: change the project start date.
continuous-monitoring.csv Excel or any other scheduling tool: every row with its dependencies, early and late dates and float
continuous-monitoring-azure-boards.csv Azure DevOps Boards: an Epic per phase and a Feature per task, gate and decision, with dates and tags (see below)
continuous-monitoring-dependencies.csv · add-azure-boards-links.ps1 The plan’s predecessor links, and a script that adds them in Azure Boards after the import
continuous-monitoring-jira.csv Jira: an Epic per phase and a Task per task, gate and decision, with dates, labels and Blocks links (see below)
continuous-monitoring.yaml The source. Edit the durations, owners and dependencies, then run python scripts/project_plans/build.py to recompute the critical path and regenerate this page, the chart and the downloads.
TipImporting this plan into Azure DevOps Boards
  1. In the project, select Boards > Queries > Import work items, choose continuous-monitoring-azure-boards.csv, check the results and select Save items. It creates one Epic per phase with a Feature under it for each task, gate and decision, with start and target dates, which is what Delivery Plans show. Epic and Feature exist in the Agile, Scrum and CMMI processes; in the Basic process, change Feature to Issue in the file first.
  2. The import can’t create dependency links or assign people. To add the predecessor links, sign in with az login, add the CLI extension with az extension add --name azure-devops, and run ./add-azure-boards-links.ps1 -Organization https://dev.azure.com/<org> -Project <project> -Plan continuous-monitoring beside continuous-monitoring-dependencies.csv. It finds the imported items by their fmw-id- tags and links each one to its predecessors.
  3. Assign people in Boards: each item carries its owner role as an Owner - … tag, and critical-path items carry Critical path. Azure Boards links don’t hold lag or start-to-start timing; each item’s description keeps them.

The dates count from the plan’s placeholder start; shift them when you set the real start. The script hasn’t been run against a live organization yet: test it on a scratch project first.

TipImporting this plan into Jira
  1. Run the CSV importer (in Jira Cloud, Settings > System > External system import > CSV) with continuous-monitoring-jira.csv. On the second step, set Date format in import file to yyyy-MM-dd.
  2. Map the columns: Work item ID to Work item ID, Work type to Work type, Parent to Parent, Summary, Description and every Labels column to their fields, Start date to the Start date field, Due date to Due date, and every Blocks column to the Blocks link type. Each phase becomes an Epic with a Task under it for each task, gate and decision; each Blocks column makes that row’s item block the item it names, which carries the plan’s dependencies.
  3. Assign people in Jira: each item carries its owner role as an owner-… label, and critical-path items carry critical-path. Jira links don’t hold lag or start-to-start timing; each description keeps them.

Test the import on a scratch project with a few rows first: the importer doesn’t remove duplicate links and Jira has no bulk delete for them. If the Blocks links don’t come through on your site, import the items first and add the links from the plan’s dependency list in a second pass, as Atlassian recommends. The dates count from the plan’s placeholder start.

TipOpening this plan in Project or Planner
  • Microsoft Project desktop opens the XML file directly, with every dependency, milestone and owner.
  • Microsoft Planner has no file import of its own: it doesn’t read XML, CSV or Excel. To bring this plan into a Planner premium plan, open the XML file in Project desktop, save it as an .mpp file, and import that through the Project Power App. Tasks, durations, dependencies and milestones come across; resources and baselines don’t, so assign owners again in Planner.
  • Without Project desktop, the CSV can feed a Power Automate flow that creates the tasks one by one, but dependencies in a premium plan need Microsoft’s Project schedule APIs, so that’s a build, not an import.
  • In a government cloud tenant, check that premium plans are available before relying on Planner for this schedule: Microsoft notes that converting a basic plan to a premium plan isn’t available in GCC.

Project for the web was retired on August 1, 2025, and Project Online on September 30, 2026; Planner is their successor. Project desktop is unaffected.