Project plan · Sample · Program

Program Master Schedule: Phases 0 to 5 and Gates G0 to G5

A sample integrated master schedule for the whole program: seven phases, six gates, the critical path and the decisions that sit on it

A sample PMP-style integrated master schedule for the Federal Modernization Program, built from Book 00, Chapters 05 and 09 and Book 01, Chapter 12: a work breakdown by phase and workstream, a computed critical path, every gate with its approver and criteria, and the intermediate decisions that hold the path, each with an owner, a decide-by week and the cost of deciding late.
NoteA sample plan, not a commitment

This is an illustrative plan built from the workbook’s books, in the form a project manager would baseline: a work breakdown, a schedule network, a computed critical path, decision points, gates and risks. The durations are illustrative, sized to the books’ roadmap weeks. Replace them with the agency’s own estimates, then baseline the result. The plan names roles, not people, and no specific agency.

Plan at a glance

Plan at a glance
Plan type Program: Phases 0 to 5 (Phase 6 is steady state)
Built from Books 00 and 01
Sponsor Executive sponsor and CIO
Plan manager Steward (program office)
Duration 48 weeks (240 working days), computed from the network
Work 47 tasks, 6 gates, 11 decision points, 1 milestone from other plans
Critical path 36 of 65 items; 4 more within 5 days of it
Calendar Week 1 = the week Phase 0 is approved; five working days a week

This is the program’s top-level schedule: every phase, every gate and the decisions leadership has to make between them, as one network. It is the schedule the complementary projects roll up to, and the one the steering committee tracks. It restates Book 01, Chapter 12 and Book 00, Chapters 05 and 09 as tasks with durations and dependencies, so the critical path is computed rather than asserted.

Schedule

Gantt chart of the Program master schedule plan over 48 weeks, grouped by phase. Critical-path tasks are red bars, other tasks are blue bars with a grey line showing their float, gates are violet diamonds, decisions are amber diamonds and milestones from other plans are green diamonds. The tables below give every date and float.

The schedule as a Gantt chart: 48 weeks, with the critical path in red.

Critical path

The computed path matches the one Book 00, Chapter 05 traces, with one departure: here the Cloud PKI certificate issuance and the Wi-Fi and VPN checks (P2.7) sit on the path, because the drift-clean hold that closes the pilot waits for them, while Book 00 runs Cloud PKI in parallel. The path runs: assessment, then the attribute taxonomy, dynamic groups and Intune design, then pilot devices, each rollout wave in turn, and the application-by-application retirement of AD-bound service principal names. Every week lost on it moves every later gate. The provisional target end state (D11) is decided with the assessment’s results, so it sits on the path at G0: it needs the sponsor and CIO in the room in week 4. Conditional Access, DNS and Arc work carry float: a slip there moves nothing until the float is used up, which is why they’re tracked by float, not by date.

The critical path, in order. Each item has zero total float: a day lost on any of them is a day lost at the finish.

The critical path
# ID Item Owner or approver When
1 D01 Approve Phase 0 and name the sponsor and steward Executive sponsor and CIO wk 1
2 P0.1 Charter accepted; owners named in the decision matrix Program office wk 1
3 P0.2 Platform host built, repository seeded, host connected through Arc Platform teams wk 1–2
4 P0.4 Read-only assessment run and committed Program office wk 3–4
5 D11 Provisional target end state: AD retired, or a dated Kerberos island Executive sponsor and CIO end of wk 4
6 G0 G0 — Ready to Plan Steward (backup: executive sponsor) end of wk 4
7 D02 Authoritative source for each attribute that drives access HR end of wk 4
8 P1.1 Attribute taxonomy finalized (M-014) Platform teams wk 5
9 P1.2 Dynamic group design tested; enterprise groups and administrative units built (M-015) Platform teams wk 6–7
10 P1.13 Pilot servers connected through Arc with machine configuration applied (M-030) Platform teams wk 7–8
11 P1.3 Intune policy design complete; pilot profiles staged (M-016) Platform teams wk 7–8
12 P1.12 Design review approved (M-021) Steward wk 8
13 G1 G1 — Foundation Complete Steward end of wk 8
14 P2.1 Sync deployed; pilot attributes, groups, AUs and delegated roles live (M-022) Platform teams wk 9–10
15 P2.2 Pilot Conditional Access and Intune policies assigned (M-024, M-025) Platform teams wk 11
16 P2.3 Pilot devices moved by pattern (M-023) Platform teams wk 12–13
17 P2.7 Cloud PKI certificates issued; Wi-Fi and VPN verified (M-028) Platform teams wk 13–14
18 P2.11 Drift-clean hold (14 days, illustrative); success criteria met (M-031) Program office wk 15–16
19 P2.4 First migrated GPOs unlinked from the pilot OUs, after 20 days of testing beside the linked GPOs Platform teams wk 16
20 P2.12 Retrospective and runbook updates committed Program office wk 16
21 G2 G2 — Pilot Clean Steward and executive sponsor (co-signed) end of wk 16
22 D07 Wave plan: which divisions, in which order Executive sponsor and steering committee end of wk 16
23 P3.1 Wave 1, first region, about 25% (M-032) Platform teams wk 17–21
24 P3.2 Wave 2, about 50% cumulative (M-033) Platform teams wk 21–25
25 P3.3 Wave 3, about 75% cumulative (M-034) Platform teams wk 25–30
26 P3.4 Wave 4, everything remaining or excepted (M-035) Platform teams wk 30–34
27 P3.6 Attribute coverage at 100%; exception register reconciled (M-037) Program office wk 34–36
28 G3 G3 — Rollout Complete Executive sponsor and steering committee end of wk 36
29 P4.6 AD-bound service principal names migrated, retired or islanded, app by app Application owners wk 37–42
30 P4.7 AD authentication volume measured below the agreed threshold Program office wk 43–44
31 G4 G4 — Legacy Quiet Steward (backup: executive sponsor) end of wk 44
32 P5.1 AD changes frozen; final assessment and evidence packet Program office wk 45
33 P5.2 Domain controllers without operations master roles demoted Platform teams wk 46
34 P5.3 Remaining domain controllers demoted or islanded; domain zones moved or retired Platform teams wk 47
35 P5.4 VMs decommissioned; final state archived; retirement record committed Platform teams wk 48
36 G5 G5 — AD Retired Executive sponsor and CIO end of wk 48

Near-critical. These items have 5 working days of float or less. Track them weekly: once their float is spent, they join the critical path.

Near-critical items
ID Item Float When
P0.3 Least-privilege service principals for Entra ID, Intune and Arc 4 d wk 1–2
P2.10 Rollback rehearsed surface by surface 4 d wk 13–14
P1.11 Every High assessment finding remediated and re-scanned 5 d wk 5–7
P1.8 Cloud PKI design; issuing CA created (M-020) 5 d wk 6–7

Decision points

Each decision is a zero-duration milestone in the network. Decide by is its late finish: the last week it can be made without moving the plan’s finish. A decision with zero float sits on the critical path, so the meeting that makes it should be booked before the plan is baselined. Decision rights follow Book 01, Chapter 09.

Decision points, by decide-by date
ID Decision Decides Needed by Decide by Float Options If it’s late
D01 Approve Phase 0 and name the sponsor and steward Executive sponsor and CIO P0.1 end of wk 1 0 (critical) Approve the four-week pre-flight; defer Nothing starts; the external clocks keep running
D02 Authoritative source for each attribute that drives access HR P1.1 end of wk 4 0 (critical) HR system per attribute; a named alternative with a dated exception The taxonomy can’t be approved, and the whole critical path waits
D11 Provisional target end state: AD retired, or a dated Kerberos island Executive sponsor and CIO G0, D09 end of wk 4 0 (critical) AD retired completely; a Kerberos island for named workloads, with an end date G0 can’t pass: owners and budgets plan without a stated goal
D04 Root of trust for device certificates Program office P1.8 end of wk 6 10 d Cloud PKI root; bring-your-own CA The PKI design and the pilot certificates wait
D03 Enforce the Conditional Access baseline CISO P1.6 end of wk 8 7 d Enforce; extend report-only; enforce with dated exceptions G1 can’t pass: the baseline must be enforced
D05 Choose the pilot division Program office P1.12 end of wk 8 18 d IT (tolerates disruption best); another division plus volunteers Pilot groups can’t be built; G1 fails its pilot-readiness criterion
D06 Device pattern for each pilot cohort Program office P2.3 end of wk 11 15 d New devices Entra joined; existing devices reset and re-enrolled; hybrid joined only with a cut date Pilot devices can’t move; the critical path waits
D07 Wave plan: which divisions, in which order Executive sponsor and steering committee P3.1 end of wk 16 0 (critical) By region, lowest risk first; by department Wave 1 can’t start; the critical path waits
D08 End dates for legacy authentication and NTLM Authorizing official P4.6 end of wk 36 100 d A dated end per protocol; a dated, risk-accepted exception per application Application owners have no date to plan against; SPN retirement slips
D09 Confirm or revise the target end state set at G0 (D11) Executive sponsor and CIO P5.2 end of wk 45 45 d Confirm the G0 target; revise it with what Phase 4 left: retire completely, or keep a documented island with an end-of-life date The demotion sequence can’t be planned
D10 Retention of AD-era logs and records Records officer P5.4 end of wk 47 55 d Retention schedule and archive location approved Domain controllers can’t be decommissioned: their logs can’t be recovered afterward

Gates

A gate opens the work that names it as a predecessor, which is usually the next phase but not always. The approver signs it against the criteria, from evidence in the repository.

Gates
Gate When Approver Criteria
G0 — Ready to Plan end of wk 4 Steward (backup: executive sponsor) Platform host operational; assessment committed; no open priority-one findings; provisional target end state recorded; no-new-AD-dependency rule in force
G1 — Foundation Complete end of wk 8 Steward Designs approved; groups and AUs drift-clean; baseline Conditional Access enforced; emergency access tested; Tier 0 in IPAM; HR feed live for the foundation scope; pilot servers connected through Arc; FIDO2 and passkeys open to Tier 0 administrators; High findings closed
G2 — Pilot Clean end of wk 16 Steward and executive sponsor (co-signed) Zero drift for the hold period; no AD-only users and no hybrid-joined PC without a cut date; no unresolved rollback trigger; retrospective committed
G3 — Rollout Complete end of wk 36 Executive sponsor and steering committee Every division past its exit gate; every HR-listed employee with valid attributes; every PC cloud-joined and every server Arc-connected, or excepted; zero cross-division drift
G4 — Legacy Quiet end of wk 44 Steward (backup: executive sponsor) Only the minimum GPOs; no AD security groups in use; every zone but the domain’s moved; user and device issuance off AD CS; every SPN migrated, retired or islanded; AD authentication below threshold
G5 — AD Retired end of wk 48 Executive sponsor and CIO Domain controllers decommissioned or a dated Kerberos island; evidence packet in the repository and the SIEM; no production dependency on AD authentication

Work breakdown and schedule

Every row, by phase. Float is total float in working days; bold rows are on the critical path. Each row links to the chapter it comes from.

Phase 0 — Pre-flight

Phase 0 — Pre-flight
ID Item Type Owner or approver Days Predecessors When Float
D01 Approve Phase 0 and name the sponsor and steward Decision Executive sponsor and CIO — — wk 1 0
P0.1 Charter accepted; owners named in the decision matrix Task Program office 3 D01 wk 1 0
P0.2 Platform host built, repository seeded, host connected through Arc Task Platform teams 7 P0.1 wk 1–2 0
P0.3 Least-privilege service principals for Entra ID, Intune and Arc Task Platform teams 3 P0.1 wk 1–2 4 d
P0.4 Read-only assessment run and committed Task Program office 10 P0.2, P0.3 wk 3–4 0
P0.5 Transactions profiled for applications proposed to move from their data Task Application owners 8 P0.1 wk 1–3 9 d
P0.6 Change process asks whether each change adds an AD dependency; exceptions to the AO Task Program office 3 P0.1 wk 1–2 14 d
D11 Provisional target end state: AD retired, or a dated Kerberos island Decision Executive sponsor and CIO — P0.4 end of wk 4 0
G0 G0 — Ready to Plan Gate Steward (backup: executive sponsor) — P0.4, P0.5, P0.6, D11 end of wk 4 0

Phase 1 — Foundation

Phase 1 — Foundation
ID Item Type Owner or approver Days Predecessors When Float
D02 Authoritative source for each attribute that drives access Decision HR — G0 end of wk 4 0
P1.1 Attribute taxonomy finalized (M-014) Task Platform teams 5 D02 wk 5 0
P1.2 Dynamic group design tested; enterprise groups and administrative units built (M-015) Task Platform teams 8 P1.1 wk 6–7 0
P1.3 Intune policy design complete; pilot profiles staged (M-016) Task Platform teams 5 P1.2 wk 7–8 0
X-IDL HR-to-cloud provisioning live for the foundation scope External ISSO (Identity Lifecycle & Provisioning plan) — — end of wk 8 0
P1.5 Conditional Access design running in report-only (M-017) Task CISO 10 G0 wk 5–6 7 d
D03 Enforce the Conditional Access baseline Decision CISO — P1.5 end of wk 6 7 d
P1.6 Baseline enforced; emergency access accounts vaulted and tested Task Platform teams 3 D03 wk 7 7 d
P1.7 Sync and DNS Private Resolver designs; resolver deployed (M-018, M-019) Task Platform teams 10 G0 wk 5–6 8 d
D04 Root of trust for device certificates Decision Program office — G0 end of wk 4 10 d
P1.8 Cloud PKI design; issuing CA created (M-020) Task Platform teams 8 D04, P1.1 wk 6–7 5 d
P1.9 IPAM covers the platform host and Tier 0 Task Platform teams 10 G0 wk 5–6 10 d
P1.10 Single sign-on; FIDO2 and passkeys open to Tier 0 administrators Task Platform teams 8 G0 wk 5–6 12 d
P1.11 Every High assessment finding remediated and re-scanned Task Platform teams 15 G0 wk 5–7 5 d
D05 Choose the pilot division Decision Program office — G0 end of wk 4 18 d
P1.12 Design review approved (M-021) Task Steward 2 P1.3, P1.7, P1.8, D05 wk 8 0
P1.13 Pilot servers connected through Arc with machine configuration applied (M-030) Task Platform teams 10 G0 +10 d wk 7–8 0
G1 G1 — Foundation Complete Gate Steward — P1.12, X-IDL, P1.6, P1.9, P1.10, P1.11, P1.13 end of wk 8 0

Phase 2 — Pilot division

Phase 2 — Pilot division
ID Item Type Owner or approver Days Predecessors When Float
D06 Device pattern for each pilot cohort Decision Program office — G1 end of wk 8 15 d
P2.1 Sync deployed; pilot attributes, groups, AUs and delegated roles live (M-022) Task Platform teams 10 G1 wk 9–10 0
P2.2 Pilot Conditional Access and Intune policies assigned (M-024, M-025) Task Platform teams 5 P2.1 wk 11 0
P2.3 Pilot devices moved by pattern (M-023) Task Platform teams 8 P2.2, D06 wk 12–13 0
P2.4 First migrated GPOs unlinked from the pilot OUs, after 20 days of testing beside the linked GPOs Task Platform teams 5 P2.2 +20 d wk 16 0
P2.5 PIM for every pilot administrator (M-026) Task Platform teams 5 P2.1 wk 11 15 d
P2.6 Division DNS migrated, DHCP re-homed, hybrid resolution validated (M-027) Task Platform teams 15 G1 wk 9–11 15 d
P2.7 Cloud PKI certificates issued; Wi-Fi and VPN verified (M-028) Task Platform teams 7 P2.3 wk 13–14 0
P2.8 Certificate-based authentication for PIV and CAC holders (M-029) Task Platform teams 8 P2.1 wk 11–12 12 d
P2.10 Rollback rehearsed surface by surface Task Platform teams 3 P2.3 wk 13–14 4 d
P2.11 Drift-clean hold (14 days, illustrative); success criteria met (M-031) Task Program office 10 P2.5, P2.6, P2.7, P2.8, P2.10 wk 15–16 0
P2.12 Retrospective and runbook updates committed Task Program office 5 P2.11 (SS) +5 d wk 16 0
G2 G2 — Pilot Clean Gate Steward and executive sponsor (co-signed) — P2.11, P2.12, P2.4 end of wk 16 0

Phase 3 — General rollout

Phase 3 — General rollout
ID Item Type Owner or approver Days Predecessors When Float
D07 Wave plan: which divisions, in which order Decision Executive sponsor and steering committee — G2 end of wk 16 0
P3.1 Wave 1, first region, about 25% (M-032) Task Platform teams 22 D07 wk 17–21 0
P3.2 Wave 2, about 50% cumulative (M-033) Task Platform teams 22 P3.1 wk 21–25 0
P3.3 Wave 3, about 75% cumulative (M-034) Task Platform teams 22 P3.2 wk 25–30 0
P3.4 Wave 4, everything remaining or excepted (M-035) Task Platform teams 22 P3.3 wk 30–34 0
P3.5 GPO links off migrated OUs after 7 clean days (M-036) Task Platform teams 5 P3.4 (SS) +17 d wk 33–34 12 d
P3.6 Attribute coverage at 100%; exception register reconciled (M-037) Task Program office 12 P3.4 wk 34–36 0
P3.7 Every server Arc-connected or excepted Task Platform teams 60 G2 wk 17–28 40 d
G3 G3 — Rollout Complete Gate Executive sponsor and steering committee — P3.5, P3.6, P3.7 end of wk 36 0

Phase 4 — Legacy retirement

Phase 4 — Legacy retirement
ID Item Type Owner or approver Days Predecessors When Float
D08 End dates for legacy authentication and NTLM Decision Authorizing official — G2 end of wk 16 100 d
P4.1 Migrated GPOs disabled and held as the rollback net (deletion follows the 90-day hold: Endpoint plan E5.2) Task Platform teams 5 G3 wk 37 20 d
P4.2 OU-based security groups retired Task Platform teams 5 P4.1 wk 38 20 d
P4.3 AD-integrated DNS zones moved, except the domain’s own zones Task Platform teams 15 G3 wk 37–39 10 d
P4.4 DHCP scopes moved off the AD-authorized servers (de-authorizing them is the Network plan’s D-N12) Task Platform teams 5 P4.3 wk 40 10 d
P4.5 User and device issuance off AD CS; smart-card logon GPO retired Task Platform teams 15 G3 wk 37–39 15 d
P4.6 AD-bound service principal names migrated, retired or islanded, app by app Task Application owners 30 G3, D08 wk 37–42 0
P4.7 AD authentication volume measured below the agreed threshold Task Program office 10 P4.6, P4.2, P4.4, P4.5 wk 43–44 0
G4 G4 — Legacy Quiet Gate Steward (backup: executive sponsor) — P4.7 end of wk 44 0

Phase 5 — AD DS retirement

Phase 5 — AD DS retirement
ID Item Type Owner or approver Days Predecessors When Float
D09 Confirm or revise the target end state set at G0 (D11) Decision Executive sponsor and CIO — G3, D11 end of wk 36 45 d
D10 Retention of AD-era logs and records Decision Records officer — G3 end of wk 36 55 d
P5.1 AD changes frozen; final assessment and evidence packet Task Program office 5 G4 wk 45 0
P5.2 Domain controllers without operations master roles demoted Task Platform teams 5 P5.1, D09 wk 46 0
P5.3 Remaining domain controllers demoted or islanded; domain zones moved or retired Task Platform teams 5 P5.2 wk 47 0
P5.4 VMs decommissioned; final state archived; retirement record committed Task Platform teams 5 P5.3, D10 wk 48 0
G5 G5 — AD Retired Gate Executive sponsor and CIO — P5.4 end of wk 48 0

Responsibility

Who owns what in this plan. Each row has one owner; consulted and informed parties follow the decision matrix.

Ownership
Owner or approver Tasks Decisions Gates
Platform teams 35 — —
Program office 8 3 —
Executive sponsor and CIO — 3 1
Application owners 2 — —
CISO 1 1 —
Executive sponsor and steering committee — 1 1
Steward 1 — 1
Steward (backup: executive sponsor) — — 2
Authorizing official — 1 —
HR — 1 —
ISSO (Identity Lifecycle & Provisioning plan) 1 — —
Records officer — 1 —
Steward and executive sponsor (co-signed) — — 1

Assumptions

  • One pilot division, then four waves of about a quarter of the estate each (Book 00, Chapter 09).
  • Durations are illustrative and sized to the roadmap’s weeks; replace them with the agency’s own estimates from the Phase 0 assessment.
  • The schedule assumes Phase 0 is approved without waiting for a vendor decision (Start Here).
  • The HR-to-cloud feed for the foundation scope comes from the Identity Lifecycle plan; its privacy basis is the longest task before go-live in that plan.
  • The source of authority for contractors is decided in the Identity Lifecycle plan (D-I3), which onboards contractor populations as their divisions move.

Schedule risks

Schedule risks
Risk Effect on the schedule Response
The assessment finds more than the plan assumed Every gate moves; the assessment is on the critical path Start the read-only assessment as soon as the platform host (P0.2) is built, weeks 3 to 4; size Phase 1 from what it finds, and re-baseline at G0
Report-only Conditional Access shows unexpected impact Uses the CA track’s float; G1 slips only if more than the float is used Start report-only in week 5, not week 7; read the sign-in logs weekly
The privacy basis for the HR feed isn’t ready G1’s HR-feed criterion fails Start the PIA update and the SORN routine-use check in Phase 0 (Identity Lifecycle plan)
Applications can’t leave AD-bound service principal names on time G4 slips week for week Set the legacy-authentication end date early (D08) so application owners plan against it

Baseline and change control

  • Baseline the plan when its first gate is approved: the YAML file, as merged, is the baseline.
  • Report weekly, green, yellow or red, against the baseline (Book 01, Chapter 12). Report float, not percent complete: a task’s float says how much slip the plan can still absorb.
  • Change the plan only through a reviewed pull request that edits the YAML and regenerates this page, so every change to a date or a dependency has an author, a reviewer and a reason.
  • Re-baseline at each gate, after the approver signs it, and whenever a critical-path decision is made late.

Download and adapt

Downloads
File Use it for
program-master-schedule.xml Microsoft Project desktop (open the XML file; it keeps the dependencies, milestones and owners). The dates start on a placeholder Monday: change the project start date.
program-master-schedule.csv Excel or any other scheduling tool: every row with its dependencies, early and late dates and float
program-master-schedule-azure-boards.csv Azure DevOps Boards: an Epic per phase and a Feature per task, gate and decision, with dates and tags (see below)
program-master-schedule-dependencies.csv · add-azure-boards-links.ps1 The plan’s predecessor links, and a script that adds them in Azure Boards after the import
program-master-schedule-jira.csv Jira: an Epic per phase and a Task per task, gate and decision, with dates, labels and Blocks links (see below)
program-master-schedule.yaml The source. Edit the durations, owners and dependencies, then run python scripts/project_plans/build.py to recompute the critical path and regenerate this page, the chart and the downloads.
TipImporting this plan into Azure DevOps Boards
  1. In the project, select Boards > Queries > Import work items, choose program-master-schedule-azure-boards.csv, check the results and select Save items. It creates one Epic per phase with a Feature under it for each task, gate and decision, with start and target dates, which is what Delivery Plans show. Epic and Feature exist in the Agile, Scrum and CMMI processes; in the Basic process, change Feature to Issue in the file first.
  2. The import can’t create dependency links or assign people. To add the predecessor links, sign in with az login, add the CLI extension with az extension add --name azure-devops, and run ./add-azure-boards-links.ps1 -Organization https://dev.azure.com/<org> -Project <project> -Plan program-master-schedule beside program-master-schedule-dependencies.csv. It finds the imported items by their fmw-id- tags and links each one to its predecessors.
  3. Assign people in Boards: each item carries its owner role as an Owner - … tag, and critical-path items carry Critical path. Azure Boards links don’t hold lag or start-to-start timing; each item’s description keeps them.

The dates count from the plan’s placeholder start; shift them when you set the real start. The script hasn’t been run against a live organization yet: test it on a scratch project first.

TipImporting this plan into Jira
  1. Run the CSV importer (in Jira Cloud, Settings > System > External system import > CSV) with program-master-schedule-jira.csv. On the second step, set Date format in import file to yyyy-MM-dd.
  2. Map the columns: Work item ID to Work item ID, Work type to Work type, Parent to Parent, Summary, Description and every Labels column to their fields, Start date to the Start date field, Due date to Due date, and every Blocks column to the Blocks link type. Each phase becomes an Epic with a Task under it for each task, gate and decision; each Blocks column makes that row’s item block the item it names, which carries the plan’s dependencies.
  3. Assign people in Jira: each item carries its owner role as an owner-… label, and critical-path items carry critical-path. Jira links don’t hold lag or start-to-start timing; each description keeps them.

Test the import on a scratch project with a few rows first: the importer doesn’t remove duplicate links and Jira has no bulk delete for them. If the Blocks links don’t come through on your site, import the items first and add the links from the plan’s dependency list in a second pass, as Atlassian recommends. The dates count from the plan’s placeholder start.

TipOpening this plan in Project or Planner
  • Microsoft Project desktop opens the XML file directly, with every dependency, milestone and owner.
  • Microsoft Planner has no file import of its own: it doesn’t read XML, CSV or Excel. To bring this plan into a Planner premium plan, open the XML file in Project desktop, save it as an .mpp file, and import that through the Project Power App. Tasks, durations, dependencies and milestones come across; resources and baselines don’t, so assign owners again in Planner.
  • Without Project desktop, the CSV can feed a Power Automate flow that creates the tasks one by one, but dependencies in a premium plan need Microsoft’s Project schedule APIs, so that’s a build, not an import.
  • In a government cloud tenant, check that premium plans are available before relying on Planner for this schedule: Microsoft notes that converting a basic plan to a premium plan isn’t available in GCC.

Project for the web was retired on August 1, 2025, and Project Online on September 30, 2026; Planner is their successor. Project desktop is unaffected.