Project plan · Sample · Project

Data Platform Identity Transformation: SQL Server from Windows Authentication to Entra ID

A sample project plan for Book 06’s runbook sequence: the consolidation gate, the authentication audit, Arc and the parallel run, NTLM restriction, the application chain and the closure record

A sample PMP-style project plan for the Data Platform Identity Transformation project, built from Book 06 and its runbooks: a work breakdown by runbook phase, a computed critical path from the pilot instance to estate closure, every gate with its approver and criteria, and the intermediate decisions (consolidation verdicts, authentication standard, NTLM phase moves, connection-string cutover) with owners and decide-by weeks.
NoteA sample plan, not a commitment

This is an illustrative plan built from the workbook’s books, in the form a project manager would baseline: a work breakdown, a schedule network, a computed critical path, decision points, gates and risks. The durations are illustrative, sized to the books’ roadmap weeks. Replace them with the agency’s own estimates, then baseline the result. The plan names roles, not people, and no specific agency.

Plan at a glance

Plan at a glance
Plan type Project: Book 06 Runbooks R01 to R10, from estate discovery to the closure record and the exception long tail
Built from Book 06
Sponsor CIO and data leadership
Plan manager Data platform project lead, with the Database Authentication, Application-Tier Identity, Secrets Lifecycle and Evidence domain leads
Duration 48 weeks (239 working days), computed from the network
Work 24 tasks, 6 gates, 10 decision points, 4 milestones from other plans
Critical path 23 of 44 items; 2 more within 5 days of it
Calendar Week 1 = the program’s Phase 0 approval; five working days a week

This plan builds the Data Platform Identity Transformation project from Book 06: SQL Server moved from Windows and SQL authentication to Microsoft Entra ID, NTLM removed after audit, and the result kept as a continuously verified closure record. Its phases follow the book’s runbook order: discovery and the consolidation gate, the authentication audit, Arc and the parallel run on a pilot instance, the estate with NTLM restriction and the access layer, the application chain, then elimination and closure. It runs inside the program master schedule: discovery belongs to the program’s Pre-flight, the pilot host follows the program’s server Arc pattern (P1.13), the group work builds on Gate G1, and NTLM restriction waits for the authorizing official’s end dates (D08). Its tail, the instances that can only close by upgrade or retirement, runs past the program’s week 48.

Schedule

Gantt chart of the Data Platform Identity Transformation plan over 48 weeks, grouped by phase. Critical-path tasks are red bars, other tasks are blue bars with a grey line showing their float, gates are violet diamonds, decisions are amber diamonds and milestones from other plans are green diamonds. The tables below give every date and float.

The schedule as a Gantt chart: 48 weeks, with the critical path in red.

Critical path

The computed path starts with discovery and the consolidation gate (Gate 0, week 5), then the NTLM baseline and Gate 1 in week 9. The program’s Arc pattern for pilot servers (P1.13, end of week 8) carries two working days of float against that, so it no longer sets the start. The pilot SQL Server host goes onto Arc after Gate 1; then come the Graph permissions, Entra authentication, the 30-day parallel run, the disable decision and Gate 2 in week 18. From there the path runs through the estate waves (D3.3), because a connection string can move only once its Entra login exists, then the application cutovers, Gate 4, the validation period, the Phase C block and Gate 5 in week 40. The exception long tail then runs to week 50, past the program’s G5 in week 48. Book 06 supports that: the estate closes when every production instance has a satisfying record or a registered exception with a sunset date, and each excepted instance closes later by its own record. The upgrade-or-retire and authentication-standard decisions (D-D3, D-D4) carry eight days of float against Gate 1; Gate 3 and the application gate conditions (D4.2) are within five days of it. The NTLM deny step waits on the authorizing official’s end dates (program D08, week 16). The application chain must be on Entra principals before the program finishes retiring AD-bound service principal names (P4.6, week 42); Gate 4 meets that with about eleven weeks of margin. Read against Book 06’s own calendar date for the block, 2027-04-01, this sample’s placeholder start puts the block in week 13, before the pilot’s parallel run ends; that conflict is settled through D08, not by compressing the parallel run.

The critical path, in order. Each item has zero total float: a day lost on any of them is a day lost at the finish.

The critical path
# ID Item Owner or approver When
1 D0.1 Toolchain installed; evidence model and dated output directories under version control Data platform team wk 1
2 D0.2 Estate inventory, read-only: the audit seed, the SPN trail and the wider sweep, fused into one inventory Data platform team wk 1–3
3 D0.3 Three rationalization lenses applied; consolidation constraints recorded Data platform team wk 3–5
4 D-D1 Retain, consolidate or retire, instance by instance CIO and data leadership end of wk 5
5 D-D2 Consolidation target for each consolidated workload CIO and data leadership end of wk 5
6 DG0 Gate 0 — Consolidation gate passed CIO and data leadership end of wk 5
7 D1.3 NTLM Phase A baseline: SPN map and collisions, auth_scheme, host Security logs, Restrict NTLM audit policies, enhanced NTLM logging Data platform team wk 5–9
8 DG1 Gate 1 — Audit read and NTLM baselined ISSO end of wk 9
9 D2.1 Pilot host on Arc: egress confirmed, onboarding service principal, managed-identity token validated, SQL Server extension deployed Server infrastructure wk 9–10
10 D2.2 Graph permissions (SQL Server 2025) or admin consent (SQL Server 2022) granted by a Privileged Role Administrator Identity engineering wk 10
11 D2.3 Entra authentication on; Entra admin group set; Entra logins and users created beside the Windows ones Data platform team wk 10–11
12 D2.4 Parallel run: 30-day observation, recorded with SQL Server Audit Data platform team wk 11–16
13 D-D5 Disable the superseded Windows logins on the pilot instance Data platform team end of wk 16
14 D2.5 Cutover: Windows logins disabled, not dropped; sa disabled and renamed; scheduled audit started Data platform team wk 16
15 DG2 Gate 2 — Pilot instance on Entra authentication ISSO end of wk 16
16 D3.3 Estate waves: every retain instance and target through Arc, Entra authentication, the parallel run and cutover Data platform team wk 16–28
17 D-D8 Connection-string cutover, application by application Application owners end of wk 20
18 D4.3 Connection strings cut over; prior configuration kept; legacy logins disabled, not dropped Application owners wk 20–29
19 DG4 Gate 4 — Application chain on Entra principals ISSO end of wk 29
20 D5.2 Validation period: closure records and the six evidence sets live and satisfied; drift treated as a violation Data platform team wk 29–37
21 D5.3 Phase C: Restrict NTLM set to deny across the estate Server infrastructure wk 37–38
22 DG5 Gate 5 — Estate closed CIO and data leadership end of wk 38
23 D5.4 Exception long tail: pre-2022 and Class 4 instances upgraded, re-platformed or retired by their sunset dates Data platform team wk 38–48

Near-critical. These items have 5 working days of float or less. Track them weekly: once their float is spent, they join the critical path.

Near-critical items
ID Item Float When
D4.2 Gate conditions prepared: identity holds its database role; change tested on a production-matching Arc stack 5 d wk 16–19
DG3 Gate 3 — Estate on Entra logins, NTLM restricted 5 d end of wk 28

Decision points

Each decision is a zero-duration milestone in the network. Decide by is its late finish: the last week it can be made without moving the plan’s finish. A decision with zero float sits on the critical path, so the meeting that makes it should be booked before the plan is baselined. Decision rights follow Book 01, Chapter 09.

Decision points, by decide-by date
ID Decision Decides Needed by Decide by Float Options If it’s late
D-D1 Retain, consolidate or retire, instance by instance CIO and data leadership DG0 end of wk 5 0 (critical) Retain; consolidate into a target (the source is then retired); retire No login may be touched: the audit, Arc and login work all wait on the classified inventory
D-D2 Consolidation target for each consolidated workload CIO and data leadership DG0 end of wk 5 0 (critical) SQL Server 2022 or 2025 on an Arc-enabled host; Azure SQL Managed Instance; Azure SQL Database or elastic pools. A dedicated target where a constraint blocks shared hosting Authentication would be migrated twice, once on the source and again on the target
D-D3 Upgrade or retire each pre-2022 retain instance CIO and data leadership DG1, D5.4 end of wk 9 8 d Upgrade to SQL Server 2022 or later and follow the Category 2-to-1 path; retire or consolidate it; keep it on a sunset-dated exception with the certificate-based interim posture (the authorizing official decides the exception) Category 3 instances have no path to Entra logins, and the exception long tail can’t be sized
D-D4 The engine authentication standard CISO DG1 end of wk 9 8 d SQL authentication refused and sa disabled and renamed on every production instance, with break-glass as an empty Windows group; a type-S login kept past migration only as a dated exception with a named compensating control. Open-ended retention isn’t an option Instances have no standard to cut over against, and the pilot can’t be signed off
D-D5 Disable the superseded Windows logins on the pilot instance Data platform team D2.5 end of wk 16 0 (critical) Disable, don’t drop, once the window’s exit criteria are met; extend the observation window The pilot can’t cut over, and the estate waves have no proven pattern
D-D7 Class and database-axis column for each application Application owners D4.2, D4.4 end of wk 17 15 d User axis: Class 3 OIDC, Class 2 SAML, Class 1 Application Proxy, Class 4 Entra Domain Services (last resort). Database axis: A configuration only, B code change, C vendor-dependent, D no Entra path today Neither migration track can be sequenced for the application
D-D8 Connection-string cutover, application by application Application owners D4.3 end of wk 20 0 (critical) Cut over in a change window once all three gate conditions hold; fund the code change (column B); carry a dated exception (columns C and D, and Class 4) The application keeps its stored credential, and its host instance can’t close
D-D6 Move Restrict NTLM from audit to deny, with exceptions from the Phase A baseline Authorizing official D3.5 end of wk 26 49 d Deny, with the excepted instances in the domain controller and client lists; stay in audit; if a missed dependency surfaces, relax to audit or add a scoped exception NTLMv2 stays open, and Phase C has no restricted baseline to tighten
D-D10 Phase C rule for instances whose interim posture isn’t in place Authorizing official D5.2 end of wk 29 70 d The Phase C date holds for them; dated exceptions with network-level isolation The long tail has no rule on the block date, and its exceptions can’t be closed
D-D9 Replacement CA and the AD CS decommission date for SQL Server’s certificates CIO and data leadership D-D10 end of wk 29 92 d Book 07’s issuers: the retained AD CS hierarchy through CyberArk Certificate Manager, moving to a standalone AD CS issuing CA under the same root when the forest retires; Microsoft Cloud PKI, which would need another enrollment path for SQL Server hosts. Either way, no decommission date until the replacement is issuing No decommission date can be set, and the certificate-based interim posture has no assured issuer

Gates

A gate opens the work that names it as a predecessor, which is usually the next phase but not always. The approver signs it against the criteria, from evidence in the repository.

Gates
Gate When Approver Criteria
Gate 0 — Consolidation gate passed end of wk 5 CIO and data leadership One row per instance, classified retain, consolidate or retire and justified by the three lenses; a target named for every consolidated workload; collation, vendor-version, compliance-isolation, failover-cluster and dependency constraints recorded; only retain instances and targets go on
Gate 1 — Audit read and NTLM baselined end of wk 9 ISSO Every retain instance and target audited and placed in Category 1, 2 or 3 with its blockers; failover cluster instances treated as Category 3; the Phase A NTLM baseline ingested by compliance monitoring; the authentication standard set
Gate 2 — Pilot instance on Entra authentication end of wk 16 ISSO Arc agent Connected; token audience https://database.windows.net/; SQL Server extension Succeeded; Entra admin set; every application and job seen on its Entra login; no remote NTLM rows; no connection arriving only on a legacy Windows login
Gate 3 — Estate on Entra logins, NTLM restricted end of wk 28 ISSO Every retain instance and target cut over after a clean parallel run; zero critical SPN collisions; Restrict NTLM deny in place with only documented exceptions; DBA administrative unit and group logins verified; a non-compliant sign-in to the SQL resource denied a token
Gate 4 — Application chain on Entra principals end of wk 29 ISSO Every application in Classes 1 to 3 connects as its Entra principal, with no NTLM or KERBEROS rows; every Class 4 or deferred application’s host instance carries a dated exception; no stored secret left in a production connection string outside a documented exception
Gate 5 — Estate closed end of wk 38 CIO and data leadership All five closure conditions hold at once on every production instance; the six evidence sets satisfied across the validation period; every excepted instance in the registry with its justification, sunset date and own closure record; the scheduled audit still running

Work breakdown and schedule

Every row, by phase. Float is total float in working days; bold rows are on the critical path. Each row links to the chapter it comes from.

Phase 0 — Prerequisites and the consolidation gate

Phase 0 — Prerequisites and the consolidation gate
ID Item Type Owner or approver Days Predecessors When Float
D0.1 Toolchain installed; evidence model and dated output directories under version control Task Data platform team 5 — wk 1 0
D0.2 Estate inventory, read-only: the audit seed, the SPN trail and the wider sweep, fused into one inventory Task Data platform team 10 D0.1 (SS) +2 d wk 1–3 0
D0.3 Three rationalization lenses applied; consolidation constraints recorded Task Data platform team 10 D0.2 wk 3–5 0
D-D1 Retain, consolidate or retire, instance by instance Decision CIO and data leadership — D0.3 end of wk 5 0
D-D2 Consolidation target for each consolidated workload Decision CIO and data leadership — D0.3 end of wk 5 0
DG0 Gate 0 — Consolidation gate passed Gate CIO and data leadership — D-D1, D-D2 end of wk 5 0

Phase 1 — The authentication audit

Phase 1 — The authentication audit
ID Item Type Owner or approver Days Predecessors When Float
D1.1 Authentication audit of the surviving set: discovery pass, then the deep audit Task Data platform team 8 DG0 wk 5–6 8 d
D1.2 Audit read: Category 1, 2 or 3 per instance; blockers listed; failover cluster instances flagged Task Data platform team 4 D1.1 wk 7 8 d
D1.3 NTLM Phase A baseline: SPN map and collisions, auth_scheme, host Security logs, Restrict NTLM audit policies, enhanced NTLM logging Task Data platform team 20 DG0 wk 5–9 0
D-D3 Upgrade or retire each pre-2022 retain instance Decision CIO and data leadership — D1.2 end of wk 7 8 d
D-D4 The engine authentication standard Decision CISO — D1.2 end of wk 7 8 d
DG1 Gate 1 — Audit read and NTLM baselined Gate ISSO — D1.3, D-D3, D-D4 end of wk 9 0

Phase 2 — The pilot instance

Phase 2 — The pilot instance
ID Item Type Owner or approver Days Predecessors When Float
X-ARC Pilot servers connected through Arc with machine configuration applied (program P1.13) External Platform teams (program) — — end of wk 8 2 d
D2.1 Pilot host on Arc: egress confirmed, onboarding service principal, managed-identity token validated, SQL Server extension deployed Task Server infrastructure 5 DG1, X-ARC wk 9–10 0
D2.2 Graph permissions (SQL Server 2025) or admin consent (SQL Server 2022) granted by a Privileged Role Administrator Task Identity engineering 2 D2.1 wk 10 0
D2.3 Entra authentication on; Entra admin group set; Entra logins and users created beside the Windows ones Task Data platform team 5 D2.2 wk 10–11 0
D2.4 Parallel run: 30-day observation, recorded with SQL Server Audit Task Data platform team 22 D2.3 wk 11–16 0
D-D5 Disable the superseded Windows logins on the pilot instance Decision Data platform team — D2.4 end of wk 16 0
D2.5 Cutover: Windows logins disabled, not dropped; sa disabled and renamed; scheduled audit started Task Data platform team 3 D-D5 wk 16 0
DG2 Gate 2 — Pilot instance on Entra authentication Gate ISSO — D2.5 end of wk 16 0

Phase 3 — The estate: logins, NTLM restriction, access layer

Phase 3 — The estate: logins, NTLM restriction, access layer
ID Item Type Owner or approver Days Predecessors When Float
X-G1 G1 — Foundation Complete: groups and AUs drift-clean, Conditional Access baseline enforced (program) External Steward (program) — — end of wk 8 86 d
D3.1 DBA administrative unit with restricted management; Groups Administrator scoped to it, eligible through PIM Task Identity engineering 3 X-G1, DG1 wk 9 84 d
D3.2 Access groups and dynamic rules verified; group logins bound; Conditional Access perimeter confirmed on the pilot Task Identity engineering 15 D3.1, DG2 wk 16–19 50 d
D3.3 Estate waves: every retain instance and target through Arc, Entra authentication, the parallel run and cutover Task Data platform team 60 DG2 wk 16–28 0
D3.4 Phase B, step 1: SPNs registered and collisions repaired, linked-server passthrough replaced, LM and NTLMv1 refused Task Data platform team 20 DG1 wk 9–13 67 d
X-D08 End dates for legacy authentication and NTLM (program D08) External Authorizing official (program) — — end of wk 16 49 d
D-D6 Move Restrict NTLM from audit to deny, with exceptions from the Phase A baseline Decision Authorizing official — D3.4, X-D08 end of wk 16 49 d
D3.5 Phase B, step 2: Restrict NTLM deny settings staged on clients, servers and domain controllers Task Server infrastructure 15 D-D6 wk 17–19 49 d
DG3 Gate 3 — Estate on Entra logins, NTLM restricted Gate ISSO — D3.2, D3.3, D3.5 end of wk 28 5 d

Phase 4 — The application chain

Phase 4 — The application chain
ID Item Type Owner or approver Days Predecessors When Float
D4.1 LDAP-bind inventory over 30 days; each application placed on both axes Task Application owners 27 DG1 wk 9–14 15 d
D-D7 Class and database-axis column for each application Decision Application owners — D4.1 end of wk 14 15 d
D4.2 Gate conditions prepared: identity holds its database role; change tested on a production-matching Arc stack Task Application owners 15 D-D7, DG2 wk 16–19 5 d
D-D8 Connection-string cutover, application by application Decision Application owners — D4.2, D3.3 (SS) +20 d end of wk 20 0
D4.3 Connection strings cut over; prior configuration kept; legacy logins disabled, not dropped Task Application owners 45 D-D8 wk 20–29 0
D4.4 Exceptions filed for Class 4 and deferred applications, sunset dates reconciled against the NTLM block Task ISSO 5 D-D7 wk 14–15 70 d
DG4 Gate 4 — Application chain on Entra principals Gate ISSO — D4.3, D4.4 end of wk 29 0
X-P46 AD-bound service principal names migrated, retired or islanded (program P4.6) External Application owners (program) — DG4 end of wk 42 fixed date

Phase 5 — Elimination, closure and the long tail

Phase 5 — Elimination, closure and the long tail
ID Item Type Owner or approver Days Predecessors When Float
D5.1 Certificate audit; SQL Server’s three AD CS dependencies mapped; CA-migration order derived Task Server infrastructure 10 DG1 wk 9–11 92 d
D-D9 Replacement CA and the AD CS decommission date for SQL Server’s certificates Decision CIO and data leadership — D5.1 end of wk 11 92 d
D-D10 Phase C rule for instances whose interim posture isn’t in place Decision Authorizing official — D4.4, D-D9 end of wk 15 70 d
D5.2 Validation period: closure records and the six evidence sets live and satisfied; drift treated as a violation Task Data platform team 40 DG3, DG4, D-D10 wk 29–37 0
D5.3 Phase C: Restrict NTLM set to deny across the estate Task Server infrastructure 5 D5.2, X-D08 wk 37–38 0
DG5 Gate 5 — Estate closed Gate CIO and data leadership — D5.3 end of wk 38 0
D5.4 Exception long tail: pre-2022 and Class 4 instances upgraded, re-platformed or retired by their sunset dates Task Data platform team 50 DG5, D-D3 wk 38–48 0

Responsibility

Who owns what in this plan. Each row has one owner; consulted and informed parties follow the decision matrix.

Ownership
Owner or approver Tasks Decisions Gates
Data platform team 13 1 —
CIO and data leadership — 4 2
Application owners 3 2 —
ISSO 1 — 4
Server infrastructure 4 — —
Identity engineering 3 — —
Authorizing official — 2 —
Application owners (program) 1 — —
Authorizing official (program) 1 — —
CISO — 1 —
Platform teams (program) 1 — —
Steward (program) 1 — —

Assumptions

  • Book 06 carries SQL Server. Other engines are inventoried only; the charter excludes non-relational platforms beyond inventory (charter).
  • Executing a large consolidation is outside this plan. The verdict is in scope, but moving databases onto targets needs its own funding decision (Book 06, Chapter 13).
  • Book 06 fixes the Phase C NTLM block at 2027-04-01, a program date, not a Microsoft one. This sample’s calendar counts from Phase 0 approval, so the block sits where the network puts it, after the validation period; the authorizing official sets the actual date through program D08.
  • The 30-day observation window holds in production; non-production may shorten it only with documented owner sign-off (Book 06, Chapter 12).
  • Durations are illustrative. The estate waves run alongside the program’s server Arc work (P3.7) and finish before its application-by-application SPN retirement (P4.6).

Schedule risks

Schedule risks
Risk Effect on the schedule Response
The pre-2022 long tail is larger than the audit first suggests The long tail outlasts the program; more instances run on the interim posture Decide upgrade or retire (D-D3) as soon as the audit is read; make most Category 3 instances retire or consolidation candidates (Book 06, Chapter 12)
The parallel-run evidence is misread A login is cut over while a client still uses Windows authentication, or a clean instance looks dirty Confirm on the pilot what auth_scheme shows for an Entra connection and filter out local connections before relying on the exit criteria (Runbook R05)
AD CS is retired before a replacement CA issues TLS certificates can’t renew and the certificate-based interim posture is lost when it’s needed most Run the certificate audit in week 9 (D5.1) and decide the issuer before any decommission date is set (Runbook R10)
Conditional Access doesn’t reach Arc-enabled SQL Server sign-ins as assumed The MFA closure condition can’t be evidenced; Gate 5 waits Confirm the Azure SQL Database target on the pilot instance (Runbook R07)
An application has no Entra path today Its host instance can’t close Give it an owner, an effort band and a dated exception at triage (Book 06, Chapter 18)

Baseline and change control

  • Baseline the plan when its first gate is approved: the YAML file, as merged, is the baseline.
  • Report weekly, green, yellow or red, against the baseline (Book 01, Chapter 12). Report float, not percent complete: a task’s float says how much slip the plan can still absorb.
  • Change the plan only through a reviewed pull request that edits the YAML and regenerates this page, so every change to a date or a dependency has an author, a reviewer and a reason.
  • Re-baseline at each gate, after the approver signs it, and whenever a critical-path decision is made late.

Download and adapt

Downloads
File Use it for
data-platform.xml Microsoft Project desktop (open the XML file; it keeps the dependencies, milestones and owners). The dates start on a placeholder Monday: change the project start date.
data-platform.csv Excel or any other scheduling tool: every row with its dependencies, early and late dates and float
data-platform-azure-boards.csv Azure DevOps Boards: an Epic per phase and a Feature per task, gate and decision, with dates and tags (see below)
data-platform-dependencies.csv · add-azure-boards-links.ps1 The plan’s predecessor links, and a script that adds them in Azure Boards after the import
data-platform-jira.csv Jira: an Epic per phase and a Task per task, gate and decision, with dates, labels and Blocks links (see below)
data-platform.yaml The source. Edit the durations, owners and dependencies, then run python scripts/project_plans/build.py to recompute the critical path and regenerate this page, the chart and the downloads.
TipImporting this plan into Azure DevOps Boards
  1. In the project, select Boards > Queries > Import work items, choose data-platform-azure-boards.csv, check the results and select Save items. It creates one Epic per phase with a Feature under it for each task, gate and decision, with start and target dates, which is what Delivery Plans show. Epic and Feature exist in the Agile, Scrum and CMMI processes; in the Basic process, change Feature to Issue in the file first.
  2. The import can’t create dependency links or assign people. To add the predecessor links, sign in with az login, add the CLI extension with az extension add --name azure-devops, and run ./add-azure-boards-links.ps1 -Organization https://dev.azure.com/<org> -Project <project> -Plan data-platform beside data-platform-dependencies.csv. It finds the imported items by their fmw-id- tags and links each one to its predecessors.
  3. Assign people in Boards: each item carries its owner role as an Owner - … tag, and critical-path items carry Critical path. Azure Boards links don’t hold lag or start-to-start timing; each item’s description keeps them.

The dates count from the plan’s placeholder start; shift them when you set the real start. The script hasn’t been run against a live organization yet: test it on a scratch project first.

TipImporting this plan into Jira
  1. Run the CSV importer (in Jira Cloud, Settings > System > External system import > CSV) with data-platform-jira.csv. On the second step, set Date format in import file to yyyy-MM-dd.
  2. Map the columns: Work item ID to Work item ID, Work type to Work type, Parent to Parent, Summary, Description and every Labels column to their fields, Start date to the Start date field, Due date to Due date, and every Blocks column to the Blocks link type. Each phase becomes an Epic with a Task under it for each task, gate and decision; each Blocks column makes that row’s item block the item it names, which carries the plan’s dependencies.
  3. Assign people in Jira: each item carries its owner role as an owner-… label, and critical-path items carry critical-path. Jira links don’t hold lag or start-to-start timing; each description keeps them.

Test the import on a scratch project with a few rows first: the importer doesn’t remove duplicate links and Jira has no bulk delete for them. If the Blocks links don’t come through on your site, import the items first and add the links from the plan’s dependency list in a second pass, as Atlassian recommends. The dates count from the plan’s placeholder start.

TipOpening this plan in Project or Planner
  • Microsoft Project desktop opens the XML file directly, with every dependency, milestone and owner.
  • Microsoft Planner has no file import of its own: it doesn’t read XML, CSV or Excel. To bring this plan into a Planner premium plan, open the XML file in Project desktop, save it as an .mpp file, and import that through the Project Power App. Tasks, durations, dependencies and milestones come across; resources and baselines don’t, so assign owners again in Planner.
  • Without Project desktop, the CSV can feed a Power Automate flow that creates the tasks one by one, but dependencies in a premium plan need Microsoft’s Project schedule APIs, so that’s a build, not an import.
  • In a government cloud tenant, check that premium plans are available before relying on Planner for this schedule: Microsoft notes that converting a basic plan to a premium plan isn’t available in GCC.

Project for the web was retired on August 1, 2025, and Project Online on September 30, 2026; Planner is their successor. Project desktop is unaffected.